Control Tower

Shipments due at an Indian port, supplier payments still to leave, and how volume, materials, on-time arrival, cost and payments have been tracking.

Arriving soon · 25 Aug 2026 – 09 Sep 2026

ShipmentMaterialJourneyStageETA
IMP-2026-0428Coking CoalOrder Confirmed · 19 Jul 2026Vessel Assigned · 21 Jul 2026Loaded at Origin · 03 Aug 2026At Sea · 07 Aug 2026At Indian Port · planned 26 Aug 2026Customs Cleared · planned 04 Sep 2026Road to Plant · planned 07 Sep 2026Received at Plant · planned 19 Sep 2026At Sea26 Aug 2026
IMP-2026-0443Met CokeOrder Confirmed · 27 Jul 2026Vessel Assigned · 29 Jul 2026Loaded at Origin · 09 Aug 2026At Sea · 13 Aug 2026At Indian Port · planned 27 Aug 2026Customs Cleared · planned 05 Sep 2026Road to Plant · planned 08 Sep 2026Received at Plant · planned 20 Sep 2026At Sea27 Aug 2026
IMP-2026-0422Chrome OreOrder Confirmed · 13 Aug 2026Vessel Assigned · 14 Aug 2026Loaded at Origin · 22 Aug 2026At Sea · planned 21 Aug 2026At Indian Port · planned 04 Sep 2026Customs Cleared · planned 13 Sep 2026Road to Plant · planned 16 Sep 2026Received at Plant · planned 28 Sep 2026Loaded at Origin04 Sep 2026
IMP-2026-0420Met CokeOrder Confirmed · 16 Aug 2026Vessel Assigned · 17 Aug 2026Loaded at Origin · planned 18 Aug 2026At Sea · planned 22 Aug 2026At Indian Port · planned 05 Sep 2026Customs Cleared · planned 14 Sep 2026Road to Plant · planned 17 Sep 2026Received at Plant · planned 29 Sep 2026Vessel Assigned05 Sep 2026
IMP-2026-0421Coking CoalOrder Confirmed · 16 Aug 2026Vessel Assigned · 18 Aug 2026Loaded at Origin · planned 20 Aug 2026At Sea · planned 24 Aug 2026At Indian Port · planned 06 Sep 2026Customs Cleared · planned 15 Sep 2026Road to Plant · planned 18 Sep 2026Received at Plant · planned 30 Sep 2026Vessel Assigned06 Sep 2026
IMP-2026-0424Coking CoalOrder Confirmed · 02 Aug 2026Vessel Assigned · 03 Aug 2026Loaded at Origin · 16 Aug 2026At Sea · 20 Aug 2026At Indian Port · planned 08 Sep 2026Customs Cleared · planned 17 Sep 2026Road to Plant · planned 20 Sep 2026Received at Plant · planned 02 Oct 2026At Sea08 Sep 2026
IMP-2026-0426Manganese OreOrder Confirmed · 12 Aug 2026Vessel Assigned · 14 Aug 2026Loaded at Origin · 23 Aug 2026At Sea · planned 21 Aug 2026At Indian Port · planned 09 Sep 2026Customs Cleared · planned 18 Sep 2026Road to Plant · planned 21 Sep 2026Received at Plant · planned 03 Oct 2026Loaded at Origin09 Sep 2026

Upcoming payments

Bowen Basin Carbon Pty Ltd is the largest share, at ₹69.2 L of cash due in this window.

Monthly import volume

Met Coke is the largest volume in the latest month, at 3,24,722 tonnes.

Supplier share

Jiangsu Hengrui Resources Co. Ltd supplied the most in this window, with 67% of arrivals on time.

Material mix

Met Coke is 30% of imported tonnage in this window.

On-time arrival trend

In the latest month, 50% of shipments arrived on or before the planned Indian-port date.

Delivered cost per tonne

Each line is actual delivered cost per tonne for that material, averaged across shipments received in the month.

Port split

Haldia handled more tonnage than Paradip. Average days at port: Haldia 15.8, Paradip 11.8.

Payments made

Jiangsu Hengrui Resources Co. Ltd is the largest share of payments made, at ₹127.36 Cr.