IMP-2026-0434

Chrome Ore · 36,959.990 MT

Meridian Commodities Pte Ltd · Hay Point → Haldia → Jamuria

Order Confirmed · 30 Jun 2026Order Confirmed30 Jun 2026Vessel Assigned · 01 Jul 2026Vessel Assigned01 Jul 2026Loaded at Origin · 10 Jul 2026Loaded at Origin10 Jul 2026At Sea · 14 Jul 2026At Sea14 Jul 2026At Indian Port · 02 Aug 2026At Indian Port02 Aug 2026Customs Cleared · 17 Aug 2026Customs Cleared17 Aug 2026+5dRoad to Plant · planned 15 Aug 2026Road to Plant15 Aug 2026Received at Plant · planned 27 Aug 2026Received at Plant27 Aug 2026

Customs Cleared

5 days past plan

Origin certificate serial does not match the Bill of Lading.

Next: Road to Plant · Jamuria

Unloaded against shipped

36,958.740 MT / 36,959.990 MT

Survey gap 1.250 MT — cargo still in the pipeline, not a plant shortfall.

Haldia needs barge transfer.

This journey

Hay Point → Haldia → Jamuria

Vessel
Not named
Bill of Lading
BL/0434/2026
Sailed
14 Jul 00:00
Arrived at Indian port
02 Aug 00:00

Delay reasons

5 days of slip across 1 stages. A stage can have more than one reason.

  • Customs assessment queue5d · Customs Cleared

    Bill of Entry assessed, duty paid, cargo released — clearance queue

Voyage

Loading map…

Stages

  1. Order ConfirmedPlanned 30 Jun 2026 · Actual 30 Jun 2026

    Owner: Procurement. Purchase order placed with the supplier

    • Purchase order placed30 Jun 2026
  2. Vessel AssignedPlanned 01 Jul 2026 · Actual 01 Jul 2026

    Owner: Supplier. Supplier has named the ship and we have accepted it

    • Vessel named01 Jul 2026
  3. Loaded at OriginPlanned 11 Jul 2026 · Actual 10 Jul 2026 · 1 day early

    Owner: Supplier. Cargo aboard, Bill of Lading issued

    • Bill of LadingVerified
    • Commercial invoiceVerified
    • Certificate of originVerified
    • Loading finished10 Jul 2026
    • Bill of Lading issued10 Jul 2026
  4. At SeaPlanned 15 Jul 2026 · Actual 14 Jul 2026 · 1 day early

    Owner: Shipping line. Sailing from China or Australia to India

    • Sailed14 Jul 2026
  5. At Indian PortPlanned 03 Aug 2026 · Actual 02 Aug 2026 · 1 day early

    Owner: Port operations. Arrived, unloading — includes barge transfer where the port is shallow

    • Arrived at Indian port02 Aug 2026
  6. Customs ClearedPlanned 12 Aug 2026 · Actual 17 Aug 2026 · 5 days late
    Customs assessment queue · 5d

    Owner: Customs agent. Bill of Entry assessed, duty paid, cargo released — clearance queue

    • Bill of EntryVerified
    • Customs cleared17 Aug 2026
  7. Road to PlantPlanned 15 Aug 2026 · Actual —

    Owner: Transporter. Trucks moving from port to the factory

    • E-way billExpected
  8. Received at PlantPlanned 27 Aug 2026 · Actual —

    Owner: Plant stores. Weighed in, plant receipt raised

    • Plant receiptExpected