Tour

IMP-2026-0439

Coking Coal · 39,361.210 MT

Bowen Basin Carbon Pty Ltd · Gladstone → Paradip → Sambalpur

Order Confirmed · 02 Jun 2026Order Confirmed02 Jun 2026Vessel Assigned · 04 Jun 2026Vessel Assigned04 Jun 2026+1dLoaded at Origin · 16 Jun 2026Loaded at Origin16 Jun 2026+3dAt Sea · 20 Jun 2026At Sea20 Jun 2026+3dAt Indian Port · 08 Jul 2026At Indian Port08 Jul 2026+2dCustoms Cleared · 17 Jul 2026Customs Cleared17 Jul 2026+2dRoad to Plant · 20 Jul 2026Road to Plant20 Jul 2026+2dReceived at Plant · 03 Aug 2026Received at Plant03 Aug 2026+4d

Quantity received against shipped

39,357.710 MT / 39,361.210 MT

Shortfall 3.500 MT · ₹104

Each leg's loss is valued at the cost accrued to that point.

Delivered cost per tonne

₹31.00

Budget ₹32.00 · −₹1.00

This journey

Gladstone → Paradip → Sambalpur

Vessel
Not named
Bill of Lading
BL/0439/2026
Sailed
20 Jun 00:00
Arrived at Indian port
08 Jul 00:00

Delay reasons

17 days of slip across 7 stages. A stage can have more than one reason.

  • Vessel named late1d · Vessel Assigned

    Supplier has named the ship and we have accepted it — behind plan

  • Supplier delay at origin3d · Loaded at Origin

    Cargo aboard, Bill of Lading issued — behind plan

  • Weather on the voyage3d · At Sea

    Sailing from China or Australia to India — weather

  • Barge transfer wait2d · At Indian Port

    Arrived, unloading — includes barge transfer where the port is shallow — behind plan

  • Customs assessment queue2d · Customs Cleared

    Bill of Entry assessed, duty paid, cargo released — clearance queue

  • Truck shortage2d · Road to Plant

    Trucks moving from port to the factory — truck shortage

  • Road traffic4d · Received at Plant

    Weighed in, plant receipt raised — behind plan

Voyage

Loading map…

Stages

  1. Order ConfirmedPlanned 02 Jun 2026 · Actual 02 Jun 2026

    Owner: Procurement. Purchase order placed with the supplier

    • Purchase order placed02 Jun 2026
  2. Vessel AssignedPlanned 03 Jun 2026 · Actual 04 Jun 2026 · 1 day late
    Vessel named late · 1d

    Owner: Supplier. Supplier has named the ship and we have accepted it — behind plan

    • Vessel named04 Jun 2026
  3. Loaded at OriginPlanned 13 Jun 2026 · Actual 16 Jun 2026 · 3 days late
    Supplier delay at origin · 3d

    Owner: Supplier. Cargo aboard, Bill of Lading issued — behind plan

    • Bill of LadingVerified
    • Commercial invoiceVerified
    • Certificate of originVerified
    • Loading finished16 Jun 2026
    • Bill of Lading issued16 Jun 2026
  4. At SeaPlanned 17 Jun 2026 · Actual 20 Jun 2026 · 3 days late
    Weather on the voyage · 3d

    Owner: Shipping line. Sailing from China or Australia to India — weather

    • Sailed20 Jun 2026
  5. At Indian PortPlanned 06 Jul 2026 · Actual 08 Jul 2026 · 2 days late
    Barge transfer wait · 2d

    Owner: Port operations. Arrived, unloading — includes barge transfer where the port is shallow — behind plan

    • Arrived at Indian port08 Jul 2026
  6. Customs ClearedPlanned 15 Jul 2026 · Actual 17 Jul 2026 · 2 days late
    Customs assessment queue · 2d

    Owner: Customs agent. Bill of Entry assessed, duty paid, cargo released — clearance queue

    • Bill of EntryVerified
    • Customs cleared17 Jul 2026
  7. Road to PlantPlanned 18 Jul 2026 · Actual 20 Jul 2026 · 2 days late
    Truck shortage · 2d

    Owner: Transporter. Trucks moving from port to the factory — truck shortage

    • E-way billVerified
    • First truck dispatched20 Jul 2026
  8. Received at PlantPlanned 30 Jul 2026 · Actual 03 Aug 2026 · 4 days late
    Road traffic · 4d

    Owner: Plant stores. Weighed in, plant receipt raised — behind plan

    • Plant receiptVerified
    • Plant receipt raised03 Aug 2026