IMP-2026-0439
Coking Coal · 39,361.210 MT
Bowen Basin Carbon Pty Ltd · Gladstone → Paradip → Sambalpur
Quantity received against shipped
39,357.710 MT / 39,361.210 MT
Shortfall 3.500 MT · ₹104
Each leg's loss is valued at the cost accrued to that point.
Delivered cost per tonne
₹31.00
Budget ₹32.00 · −₹1.00
This journey
Gladstone → Paradip → Sambalpur
- Vessel
- Not named
- Bill of Lading
- BL/0439/2026
- Sailed
- 20 Jun 00:00
- Arrived at Indian port
- 08 Jul 00:00
Delay reasons
17 days of slip across 7 stages. A stage can have more than one reason.
- Vessel named late1d · Vessel Assigned
Supplier has named the ship and we have accepted it — behind plan
- Supplier delay at origin3d · Loaded at Origin
Cargo aboard, Bill of Lading issued — behind plan
- Weather on the voyage3d · At Sea
Sailing from China or Australia to India — weather
- Barge transfer wait2d · At Indian Port
Arrived, unloading — includes barge transfer where the port is shallow — behind plan
- Customs assessment queue2d · Customs Cleared
Bill of Entry assessed, duty paid, cargo released — clearance queue
- Truck shortage2d · Road to Plant
Trucks moving from port to the factory — truck shortage
- Road traffic4d · Received at Plant
Weighed in, plant receipt raised — behind plan
Voyage
Stages
Order ConfirmedPlanned 02 Jun 2026 · Actual 02 Jun 2026
Owner: Procurement. Purchase order placed with the supplier
- Purchase order placed02 Jun 2026
Vessel AssignedPlanned 03 Jun 2026 · Actual 04 Jun 2026 · 1 day late
Vessel named late · 1dOwner: Supplier. Supplier has named the ship and we have accepted it — behind plan
- Vessel named04 Jun 2026
Loaded at OriginPlanned 13 Jun 2026 · Actual 16 Jun 2026 · 3 days late
Supplier delay at origin · 3dOwner: Supplier. Cargo aboard, Bill of Lading issued — behind plan
- Bill of LadingVerified
- Commercial invoiceVerified
- Certificate of originVerified
- Loading finished16 Jun 2026
- Bill of Lading issued16 Jun 2026
At SeaPlanned 17 Jun 2026 · Actual 20 Jun 2026 · 3 days late
Weather on the voyage · 3dOwner: Shipping line. Sailing from China or Australia to India — weather
- Sailed20 Jun 2026
At Indian PortPlanned 06 Jul 2026 · Actual 08 Jul 2026 · 2 days late
Barge transfer wait · 2dOwner: Port operations. Arrived, unloading — includes barge transfer where the port is shallow — behind plan
- Arrived at Indian port08 Jul 2026
Customs ClearedPlanned 15 Jul 2026 · Actual 17 Jul 2026 · 2 days late
Customs assessment queue · 2dOwner: Customs agent. Bill of Entry assessed, duty paid, cargo released — clearance queue
- Bill of EntryVerified
- Customs cleared17 Jul 2026
Road to PlantPlanned 18 Jul 2026 · Actual 20 Jul 2026 · 2 days late
Truck shortage · 2dOwner: Transporter. Trucks moving from port to the factory — truck shortage
- E-way billVerified
- First truck dispatched20 Jul 2026
Received at PlantPlanned 30 Jul 2026 · Actual 03 Aug 2026 · 4 days late
Road traffic · 4dOwner: Plant stores. Weighed in, plant receipt raised — behind plan
- Plant receiptVerified
- Plant receipt raised03 Aug 2026