IMP-2026-0507
Manganese Ore · 41,465.210 MT
Jiangsu Hengrui Resources Co. Ltd · Rizhao → Paradip → Sambalpur · MV Jade Horizon
Quantity received against shipped
41,462.430 MT / 41,465.210 MT
Shortfall 2.780 MT · ₹82
Each leg's loss is valued at the cost accrued to that point.
Delivered cost per tonne
₹31.00
Budget ₹31.00 · +₹0.00
This journey
Rizhao → Paradip → Sambalpur
- Vessel
- MV Jade Horizon
- Bill of Lading
- BL/0507/2026
- Sailed
- 25 Jan 00:00
- Arrived at Indian port
- 08 Feb 00:00
Delay reasons
13 days of slip across 7 stages. A stage can have more than one reason.
- Vessel named late1d · Vessel Assigned
Supplier has named the ship and we have accepted it — behind plan
- Supplier delay at origin2d · Loaded at Origin
Cargo aboard, Bill of Lading issued — behind plan
- Weather on the voyage2d · At Sea
Sailing from China or Australia to India — weather
- Barge transfer wait2d · At Indian Port
Arrived, unloading — includes barge transfer where the port is shallow — behind plan
- Customs assessment queue1d · Customs Cleared
Bill of Entry assessed, duty paid, cargo released — clearance queue
- Truck shortage2d · Road to Plant
Trucks moving from port to the factory — truck shortage
- Road traffic3d · Received at Plant
Weighed in, plant receipt raised — behind plan
Voyage
Stages
Order ConfirmedPlanned 08 Jan 2026 · Actual 08 Jan 2026
Owner: Procurement. Purchase order placed with the supplier
- Purchase order placed08 Jan 2026
Vessel AssignedPlanned 09 Jan 2026 · Actual 10 Jan 2026 · 1 day late
Vessel named late · 1dOwner: Supplier. Supplier has named the ship and we have accepted it — behind plan
- Vessel named10 Jan 2026
Loaded at OriginPlanned 19 Jan 2026 · Actual 21 Jan 2026 · 2 days late
Supplier delay at origin · 2dOwner: Supplier. Cargo aboard, Bill of Lading issued — behind plan
- Bill of LadingVerified
- Commercial invoiceVerified
- Certificate of originVerified
- Loading finished21 Jan 2026
- Bill of Lading issued21 Jan 2026
At SeaPlanned 23 Jan 2026 · Actual 25 Jan 2026 · 2 days late
Weather on the voyage · 2dOwner: Shipping line. Sailing from China or Australia to India — weather
- Sailed25 Jan 2026
At Indian PortPlanned 06 Feb 2026 · Actual 08 Feb 2026 · 2 days late
Barge transfer wait · 2dOwner: Port operations. Arrived, unloading — includes barge transfer where the port is shallow — behind plan
- Arrived at Indian port08 Feb 2026
Customs ClearedPlanned 15 Feb 2026 · Actual 16 Feb 2026 · 1 day late
Customs assessment queue · 1dOwner: Customs agent. Bill of Entry assessed, duty paid, cargo released — clearance queue
- Bill of EntryVerified
- Customs cleared16 Feb 2026
Road to PlantPlanned 18 Feb 2026 · Actual 20 Feb 2026 · 2 days late
Truck shortage · 2dOwner: Transporter. Trucks moving from port to the factory — truck shortage
- E-way billVerified
- First truck dispatched20 Feb 2026
Received at PlantPlanned 02 Mar 2026 · Actual 05 Mar 2026 · 3 days late
Road traffic · 3dOwner: Plant stores. Weighed in, plant receipt raised — behind plan
- Plant receiptVerified
- Plant receipt raised05 Mar 2026