IMP-2026-0507

Manganese Ore · 41,465.210 MT

Jiangsu Hengrui Resources Co. Ltd · Rizhao → Paradip → Sambalpur · MV Jade Horizon

Order Confirmed · 08 Jan 2026Order Confirmed08 Jan 2026Vessel Assigned · 10 Jan 2026Vessel Assigned10 Jan 2026+1dLoaded at Origin · 21 Jan 2026Loaded at Origin21 Jan 2026+2dAt Sea · 25 Jan 2026At Sea25 Jan 2026+2dAt Indian Port · 08 Feb 2026At Indian Port08 Feb 2026+2dCustoms Cleared · 16 Feb 2026Customs Cleared16 Feb 2026+1dRoad to Plant · 20 Feb 2026Road to Plant20 Feb 2026+2dReceived at Plant · 05 Mar 2026Received at Plant05 Mar 2026+3d

Quantity received against shipped

41,462.430 MT / 41,465.210 MT

Shortfall 2.780 MT · ₹82

Each leg's loss is valued at the cost accrued to that point.

Delivered cost per tonne

₹31.00

Budget ₹31.00 · +₹0.00

This journey

Rizhao → Paradip → Sambalpur

Vessel
MV Jade Horizon
Bill of Lading
BL/0507/2026
Sailed
25 Jan 00:00
Arrived at Indian port
08 Feb 00:00

Delay reasons

13 days of slip across 7 stages. A stage can have more than one reason.

  • Vessel named late1d · Vessel Assigned

    Supplier has named the ship and we have accepted it — behind plan

  • Supplier delay at origin2d · Loaded at Origin

    Cargo aboard, Bill of Lading issued — behind plan

  • Weather on the voyage2d · At Sea

    Sailing from China or Australia to India — weather

  • Barge transfer wait2d · At Indian Port

    Arrived, unloading — includes barge transfer where the port is shallow — behind plan

  • Customs assessment queue1d · Customs Cleared

    Bill of Entry assessed, duty paid, cargo released — clearance queue

  • Truck shortage2d · Road to Plant

    Trucks moving from port to the factory — truck shortage

  • Road traffic3d · Received at Plant

    Weighed in, plant receipt raised — behind plan

Voyage

Loading map…

Stages

  1. Order ConfirmedPlanned 08 Jan 2026 · Actual 08 Jan 2026

    Owner: Procurement. Purchase order placed with the supplier

    • Purchase order placed08 Jan 2026
  2. Vessel AssignedPlanned 09 Jan 2026 · Actual 10 Jan 2026 · 1 day late
    Vessel named late · 1d

    Owner: Supplier. Supplier has named the ship and we have accepted it — behind plan

    • Vessel named10 Jan 2026
  3. Loaded at OriginPlanned 19 Jan 2026 · Actual 21 Jan 2026 · 2 days late
    Supplier delay at origin · 2d

    Owner: Supplier. Cargo aboard, Bill of Lading issued — behind plan

    • Bill of LadingVerified
    • Commercial invoiceVerified
    • Certificate of originVerified
    • Loading finished21 Jan 2026
    • Bill of Lading issued21 Jan 2026
  4. At SeaPlanned 23 Jan 2026 · Actual 25 Jan 2026 · 2 days late
    Weather on the voyage · 2d

    Owner: Shipping line. Sailing from China or Australia to India — weather

    • Sailed25 Jan 2026
  5. At Indian PortPlanned 06 Feb 2026 · Actual 08 Feb 2026 · 2 days late
    Barge transfer wait · 2d

    Owner: Port operations. Arrived, unloading — includes barge transfer where the port is shallow — behind plan

    • Arrived at Indian port08 Feb 2026
  6. Customs ClearedPlanned 15 Feb 2026 · Actual 16 Feb 2026 · 1 day late
    Customs assessment queue · 1d

    Owner: Customs agent. Bill of Entry assessed, duty paid, cargo released — clearance queue

    • Bill of EntryVerified
    • Customs cleared16 Feb 2026
  7. Road to PlantPlanned 18 Feb 2026 · Actual 20 Feb 2026 · 2 days late
    Truck shortage · 2d

    Owner: Transporter. Trucks moving from port to the factory — truck shortage

    • E-way billVerified
    • First truck dispatched20 Feb 2026
  8. Received at PlantPlanned 02 Mar 2026 · Actual 05 Mar 2026 · 3 days late
    Road traffic · 3d

    Owner: Plant stores. Weighed in, plant receipt raised — behind plan

    • Plant receiptVerified
    • Plant receipt raised05 Mar 2026