IMP-2026-0508
Chrome Ore · 59,792.470 MT
Hebei Metallurgical Trading Co. Ltd · Lianyungang → Haldia → Jamuria · MV Coral Trader
Quantity received against shipped
59,789.560 MT / 59,792.470 MT
Shortfall 2.910 MT · ₹87
Each leg's loss is valued at the cost accrued to that point.
Delivered cost per tonne
₹32.00
Budget ₹31.00 · +₹1.00
This journey
Lianyungang → Haldia → Jamuria
- Vessel
- MV Coral Trader
- Bill of Lading
- BL/0508/2026
- Sailed
- 16 Feb 00:00
- Arrived at Indian port
- 02 Mar 00:00
Delay reasons
26 days of slip across 7 stages. A stage can have more than one reason.
- Vessel named late1d · Vessel Assigned
Supplier has named the ship and we have accepted it — behind plan
- Supplier delay at origin1d · Loaded at Origin
Cargo aboard, Bill of Lading issued — behind plan
- Weather on the voyage1d · At Sea
Sailing from China or Australia to India — weather
- Barge transfer wait1d · At Indian Port
Arrived, unloading — includes barge transfer where the port is shallow — behind plan
- Customs assessment queue7d · Customs Cleared
Bill of Entry assessed, duty paid, cargo released — clearance queue
- Truck shortage8d · Road to Plant
Trucks moving from port to the factory — truck shortage
- Road traffic7d · Received at Plant
Weighed in, plant receipt raised — behind plan
Voyage
Stages
Order ConfirmedPlanned 31 Jan 2026 · Actual 31 Jan 2026
Owner: Procurement. Purchase order placed with the supplier
- Purchase order placed31 Jan 2026
Vessel AssignedPlanned 01 Feb 2026 · Actual 02 Feb 2026 · 1 day late
Vessel named late · 1dOwner: Supplier. Supplier has named the ship and we have accepted it — behind plan
- Vessel named02 Feb 2026
Loaded at OriginPlanned 11 Feb 2026 · Actual 12 Feb 2026 · 1 day late
Supplier delay at origin · 1dOwner: Supplier. Cargo aboard, Bill of Lading issued — behind plan
- Bill of LadingVerified
- Commercial invoiceVerified
- Certificate of originVerified
- Loading finished12 Feb 2026
- Bill of Lading issued12 Feb 2026
At SeaPlanned 15 Feb 2026 · Actual 16 Feb 2026 · 1 day late
Weather on the voyage · 1dOwner: Shipping line. Sailing from China or Australia to India — weather
- Sailed16 Feb 2026
At Indian PortPlanned 01 Mar 2026 · Actual 02 Mar 2026 · 1 day late
Barge transfer wait · 1dOwner: Port operations. Arrived, unloading — includes barge transfer where the port is shallow — behind plan
- Arrived at Indian port02 Mar 2026
Customs ClearedPlanned 10 Mar 2026 · Actual 17 Mar 2026 · 7 days late
Customs assessment queue · 7dOwner: Customs agent. Bill of Entry assessed, duty paid, cargo released — clearance queue
- Bill of EntryVerified
- Customs cleared17 Mar 2026
Road to PlantPlanned 13 Mar 2026 · Actual 21 Mar 2026 · 8 days late
Truck shortage · 8dOwner: Transporter. Trucks moving from port to the factory — truck shortage
- E-way billVerified
- First truck dispatched21 Mar 2026
Received at PlantPlanned 25 Mar 2026 · Actual 01 Apr 2026 · 7 days late
Road traffic · 7dOwner: Plant stores. Weighed in, plant receipt raised — behind plan
- Plant receiptVerified
- Plant receipt raised01 Apr 2026