IMP-2026-0511
Coking Coal · 26,335.210 MT
Pilbara Bulk Minerals Pty Ltd · Port Hedland → Paradip → Sambalpur · MV Bay of Bengal
Quantity received against shipped
26,332.760 MT / 26,335.210 MT
Shortfall 2.450 MT · ₹73
Each leg's loss is valued at the cost accrued to that point.
Delivered cost per tonne
₹31.00
Budget ₹31.00 · +₹0.00
This journey
Port Hedland → Paradip → Sambalpur
- Vessel
- MV Bay of Bengal
- Bill of Lading
- BL/0511/2026
- Sailed
- 14 May 00:00
- Arrived at Indian port
- 27 May 00:00
This shipment is running to plan.
Voyage
Stages
Order ConfirmedPlanned 01 May 2026 · Actual 01 May 2026
Owner: Procurement. Purchase order placed with the supplier
- Purchase order placed01 May 2026
Vessel AssignedPlanned 02 May 2026 · Actual 02 May 2026
Owner: Supplier. Supplier has named the ship and we have accepted it
- Vessel named02 May 2026
Loaded at OriginPlanned 12 May 2026 · Actual 09 May 2026 · 3 days early
Owner: Supplier. Cargo aboard, Bill of Lading issued
- Bill of LadingVerified
- Commercial invoiceVerified
- Certificate of originVerified
- Loading finished09 May 2026
- Bill of Lading issued09 May 2026
At SeaPlanned 16 May 2026 · Actual 14 May 2026 · 2 days early
Owner: Shipping line. Sailing from China or Australia to India
- Sailed14 May 2026
At Indian PortPlanned 29 May 2026 · Actual 27 May 2026 · 2 days early
Owner: Port operations. Arrived, unloading — includes barge transfer where the port is shallow
- Arrived at Indian port27 May 2026
Customs ClearedPlanned 07 Jun 2026 · Actual 04 Jun 2026 · 3 days early
Owner: Customs agent. Bill of Entry assessed, duty paid, cargo released
- Bill of EntryVerified
- Customs cleared04 Jun 2026
Road to PlantPlanned 10 Jun 2026 · Actual 07 Jun 2026 · 3 days early
Owner: Transporter. Trucks moving from port to the factory
- E-way billVerified
- First truck dispatched07 Jun 2026
Received at PlantPlanned 22 Jun 2026 · Actual 21 Jun 2026 · 1 day early
Owner: Plant stores. Weighed in, plant receipt raised
- Plant receiptVerified
- Plant receipt raised21 Jun 2026