Each purchase contract in full: what we agreed to buy, at what price and quality, how laytime is counted, and how it is paid for. The risk panel at the top reads the clauses on their own terms and flags the ones that can cost money if the voyage goes badly — uncapped demurrage above all.

Quantity tolerance
The band either side of the contract quantity that the seller may ship at their option, shown as an actual tonnage range.
Laytime terms
The discharge rate, what counts as laytime, and the daily demurrage rate. These are the inputs to every laytime calculation on that contract's cargoes.
Risk flags
Clauses read straight from the contract. Nothing here depends on how any particular shipment went.

Read the full guide for this screen · written for Commercial

← All contracts

CTR-SM-2026-104

shippedCIF

Low Ash Metallurgical Coke bought from Meridian Commodities Pte Ltd for discharge at Kolkata Dock System. Signed 01 Nov 2025.

Contract risk

Clauses that can cost us money if the voyage goes badly. Read from the contract terms alone — nothing here depends on how this shipment actually went.

  • Charter party is not disclosed

    warning

    Under CIF the seller charters the vessel and we never see the charter party. Laytime exceptions are argued from the Statement of Facts alone, with no head-charter wording to fall back on.

  • Lighterage time counts as laytime

    warning

    Waiting for barges at the anchorage runs against our allowance, even though barge supply is a port constraint rather than our delay.

Commercial terms

Seller

Meridian Commodities Pte Ltd

Commodity

Low Ash Metallurgical Coke

Discharge port

Kolkata Dock System

Base price

$284.00 / MT dry basis

Contract quantity

31,000.000 MT
accepted band 29,450.000 MT 32,550.000 MT

Laycan

01 Aug 2026 25 Aug 2026
the window in which the vessel must present

Who carries what under CIF

Ocean freight

seller

Marine insurance

seller

Load port demurrage

seller

Discharge demurrage

us

Risk passes

at load port

Quality specification

Typical is what the seller declares. Cargo outside the maximum or minimum is repriced by the adjustment rules below.

ParameterTypicalMaximumMinimum
Ash ASH12.00 %12.50 %

Price adjustment rules

ASH deduct $2.00 per tonne for every 0.50 % beyond 12.50 %, pro rata. Cargo past 14.50 % may be rejected.

Laytime and demurrage terms

Laytime is the free time we get to discharge. Run past it and Demurrage is payable for every day over.

Discharge rate

8,000 MT per day

Counted as

Weather working days, Sundays and holidays excepted

Turn time

6 hours

Notice of Readiness may be tendered

Whether in port or not

Demurrage rate

$15,000.00 per day

Despatch rate

$7,500.00 per day earned back if we finish early

Daily cap

$15,000.00

Rebuttal window

30 days to dispute a claim

Settlement window

60 days to settle it
lighterage time countsweather stoppages excludedfirst shifting excluded

Payment terms

Instrument

Letter of credit at sight

Provisional payment

90% on Bill of Lading date

Final payment

10% on Discharge port analysis certificate

Credit period

at sight

Parcels shipped against this contract

ParcelB/LB/L dateB/L quantityStatus
PCL-2026-0504BL/050410 Jun 202631,000.000 MTIn transit

31,000.000 MT shipped against 31,000.000 MT contracted.