IMP-2026-0430
Met Coke · 132,129.990 MT
Jiangsu Hengrui Resources Co. Ltd · Jingtang → Haldia → Jamuria · MV Cape Resolve
At Indian Port
1 day past plan
Arrived, unloading — includes barge transfer where the port is shallow — behind plan
Next: Customs Cleared
Unloaded against shipped
132,128.940 MT / 132,129.990 MT
Survey gap 1.050 MT — cargo still in the pipeline, not a plant shortfall.
Haldia needs barge transfer.
What this cargo is
Met Coke · Carbon · Jiangsu Hengrui Resources Co. Ltd → Jamuria
Blast-furnace coke — ash, fixed carbon and CSR decide furnace performance.
- Delivery terms
- CIF
- Price basis
- Dry
- Intended plant
- Jamuria
Ordered → shipped → unloaded → received at plant
Shortfall 132,129.990 MT · ₹41.0 L
Show measurement detail
| Leg | From | To | Variance |
|---|---|---|---|
| Ordered → shipped | 132,130.100 MT | 132,129.990 MT | 0.110 MT |
| BILL_OF_LADING → DISCHARGE_WEIGHT_SURVEY | 132,129.990 MT | 132,128.940 MT | 1.050 MT |
Wet outturn 132,128.940 MT · dry outturn 125,258.235 MT on the contract dry basis.
Largest movement on BILL_OF_LADING → DISCHARGE_WEIGHT_SURVEY: 1.050 MT · Shipping line
Measurement certificates
| Measurement | Quantity | Date | Certificate |
|---|---|---|---|
| Contract | 132,130.100 MT | 12 Jun 2026 | CTR-SM-2026-0430 |
| Bill of Lading | 132,129.990 MT | 01 Aug 2026 | BL/0430/2026 |
| Indian-port weight survey | 132,128.940 MT | 19 Aug 2026 | WS/0430 |
Unloading
This cargo needs barge transfer at a shallow Indian port before the road run to Jamuria.
| Stage | Vessel | Quantity | Started | Completed |
|---|---|---|---|---|
| Main vessel at anchorage | MV Cape Resolve | 132,129.990 MT | 19 Aug 2026 | — |
| Barge transfer | BG Ganga Star 1 | 15,855.599 MT | 19 Aug 2026 | — |
| Barge transfer | BG Ganga Star 2 | 15,855.599 MT | 19 Aug 2026 | — |
| Barge transfer | BG Hooghly Pride | 17,176.899 MT | 19 Aug 2026 | — |
| Barge transfer | BG Hooghly Valour | 15,855.599 MT | 19 Aug 2026 | — |
| Main vessel at berth | MV Cape Resolve | 67,386.295 MT | — | — |
Quality for steelmaking
| Parameter | Contract | Origin | Indian port | Result |
|---|---|---|---|---|
Ash Lower ash leaves more carbon for the furnace. | 50.00% | 48.30% | 48.30% | Pass |
Moisture Moisture is deducted when the contract prices on a dry basis. | 50.00% | 49.50% | 49.50% | Pass |
Fixed Carbon Fixed carbon available for reduction in the furnace. | 50.00% | 50.70% | 50.70% | Pass |
Coke Strength after Reaction Coke strength after reaction — higher CSR holds the blast-furnace burden. | 50.00 | 51.90 | 51.90 | Pass |
Contract typical against origin and Indian-port Quality test. Moisture on the pricing test is 49.50%.