IMP-2026-0435
Limestone · 37,441.210 MT
Rizhao Carbon Materials Co. Ltd · Rizhao → Paradip → Sambalpur
Customs Cleared
3 days past plan
Bill of Entry assessed, duty paid, cargo released — clearance queue
Next: Road to Plant · Sambalpur
Unloaded against shipped
37,439.910 MT / 37,441.210 MT
Survey gap 1.300 MT — cargo still in the pipeline, not a plant shortfall.
This journey
Rizhao → Paradip → Sambalpur
- Vessel
- Not named
- Bill of Lading
- BL/0435/2026
- Sailed
- 30 Jul 00:00
- Arrived at Indian port
- 13 Aug 00:00
Delay reasons
10 days of slip across 5 stages. A stage can have more than one reason.
- Vessel named late1d · Vessel Assigned
Supplier has named the ship and we have accepted it — behind plan
- Supplier delay at origin2d · Loaded at Origin
Cargo aboard, Bill of Lading issued — behind plan
- Weather on the voyage2d · At Sea
Sailing from China or Australia to India — weather
- Barge transfer wait2d · At Indian Port
Arrived, unloading — includes barge transfer where the port is shallow — behind plan
- Customs assessment queue3d · Customs Cleared
Bill of Entry assessed, duty paid, cargo released — clearance queue
Voyage
Stages
Order ConfirmedPlanned 13 Jul 2026 · Actual 13 Jul 2026
Owner: Procurement. Purchase order placed with the supplier
- Purchase order placed13 Jul 2026
Vessel AssignedPlanned 14 Jul 2026 · Actual 15 Jul 2026 · 1 day late
Vessel named late · 1dOwner: Supplier. Supplier has named the ship and we have accepted it — behind plan
- Vessel named15 Jul 2026
Loaded at OriginPlanned 24 Jul 2026 · Actual 26 Jul 2026 · 2 days late
Supplier delay at origin · 2dOwner: Supplier. Cargo aboard, Bill of Lading issued — behind plan
- Bill of LadingVerified
- Commercial invoiceVerified
- Certificate of originVerified
- Loading finished26 Jul 2026
- Bill of Lading issued26 Jul 2026
At SeaPlanned 28 Jul 2026 · Actual 30 Jul 2026 · 2 days late
Weather on the voyage · 2dOwner: Shipping line. Sailing from China or Australia to India — weather
- Sailed30 Jul 2026
At Indian PortPlanned 11 Aug 2026 · Actual 13 Aug 2026 · 2 days late
Barge transfer wait · 2dOwner: Port operations. Arrived, unloading — includes barge transfer where the port is shallow — behind plan
- Arrived at Indian port13 Aug 2026
Customs ClearedPlanned 20 Aug 2026 · Actual 23 Aug 2026 · 3 days late
Customs assessment queue · 3dOwner: Customs agent. Bill of Entry assessed, duty paid, cargo released — clearance queue
- Bill of EntryVerified
- Customs cleared23 Aug 2026
Road to PlantPlanned 23 Aug 2026 · Actual —
Owner: Transporter. Trucks moving from port to the factory
- E-way billExpected
Received at PlantPlanned 04 Sep 2026 · Actual —
Owner: Plant stores. Weighed in, plant receipt raised
- Plant receiptExpected