Demo date · 25 Aug 2026
Tour

IMP-2026-0437

Met Coke · 38,400.930 MT

Jiangsu Hengrui Resources Co. Ltd · Lianyungang → Paradip → Sambalpur

Order Confirmed · 30 Jun 2026Order Confirmed30 Jun 2026Vessel Assigned · 02 Jul 2026Vessel Assigned02 Jul 2026+1dLoaded at Origin · 11 Jul 2026Loaded at Origin11 Jul 2026At Sea · 15 Jul 2026At Sea15 Jul 2026At Indian Port · 29 Jul 2026At Indian Port29 Jul 2026Customs Cleared · 07 Aug 2026Customs Cleared07 Aug 2026Road to Plant · 10 Aug 2026Road to Plant10 Aug 2026Received at Plant · planned 22 Aug 2026Received at Plant22 Aug 2026

Road to Plant

On plan

Supplier has named the ship and we have accepted it — behind plan

Next: Received at Plant · Sambalpur

Trucks on the road

2 of 5 trucks on the road

E-way bill issued on 5 trucks. 3 received at the plant.

Destination Sambalpur.

This journey

Lianyungang → Paradip → Sambalpur

Vessel
Not named
Bill of Lading
BL/0437/2026
Sailed
15 Jul 00:00
Arrived at Indian port
29 Jul 00:00

Delay reasons

1 days of slip across 1 stages. A stage can have more than one reason.

  • Vessel named late1d · Vessel Assigned

    Supplier has named the ship and we have accepted it — behind plan

Voyage

Loading map…

Stages

  1. Order ConfirmedPlanned 30 Jun 2026 · Actual 30 Jun 2026

    Owner: Procurement. Purchase order placed with the supplier

    • Purchase order placed30 Jun 2026
  2. Vessel AssignedPlanned 01 Jul 2026 · Actual 02 Jul 2026 · 1 day late
    Vessel named late · 1d

    Owner: Supplier. Supplier has named the ship and we have accepted it — behind plan

    • Vessel named02 Jul 2026
  3. Loaded at OriginPlanned 11 Jul 2026 · Actual 11 Jul 2026

    Owner: Supplier. Cargo aboard, Bill of Lading issued

    • Bill of LadingVerified
    • Commercial invoiceVerified
    • Certificate of originVerified
    • Loading finished11 Jul 2026
    • Bill of Lading issued11 Jul 2026
  4. At SeaPlanned 15 Jul 2026 · Actual 15 Jul 2026

    Owner: Shipping line. Sailing from China or Australia to India

    • Sailed15 Jul 2026
  5. At Indian PortPlanned 29 Jul 2026 · Actual 29 Jul 2026

    Owner: Port operations. Arrived, unloading — includes barge transfer where the port is shallow

    • Arrived at Indian port29 Jul 2026
  6. Customs ClearedPlanned 07 Aug 2026 · Actual 07 Aug 2026

    Owner: Customs agent. Bill of Entry assessed, duty paid, cargo released

    • Bill of EntryVerified
    • Customs cleared07 Aug 2026
  7. Road to PlantPlanned 10 Aug 2026 · Actual 10 Aug 2026

    Owner: Transporter. Trucks moving from port to the factory

    • E-way billVerified
    • First truck dispatched10 Aug 2026
  8. Received at PlantPlanned 22 Aug 2026 · Actual —

    Owner: Plant stores. Weighed in, plant receipt raised

    • Plant receiptExpected