Tour

IMP-2026-0438

Manganese Ore · 38,879.990 MT

Hebei Metallurgical Trading Co. Ltd · Jingtang → Haldia → Jamuria

Order Confirmed · 28 Jun 2026Order Confirmed28 Jun 2026Vessel Assigned · 29 Jun 2026Vessel Assigned29 Jun 2026Loaded at Origin · 10 Jul 2026Loaded at Origin10 Jul 2026+1dAt Sea · 15 Jul 2026At Sea15 Jul 2026+2dAt Indian Port · 29 Jul 2026At Indian Port29 Jul 2026+2dCustoms Cleared · 12 Aug 2026Customs Cleared12 Aug 2026+7dRoad to Plant · 15 Aug 2026Road to Plant15 Aug 2026+7dReceived at Plant · planned 20 Aug 2026Received at Plant20 Aug 2026

Road to Plant

7 days past plan

Trucks moving from port to the factory — truck shortage

Next: Received at Plant · Jamuria

Trucks on the road

2 of 5 trucks on the road

E-way bill issued on 5 trucks. 3 received at the plant.

Destination Jamuria.

This journey

Jingtang → Haldia → Jamuria

Vessel
Not named
Bill of Lading
BL/0438/2026
Sailed
15 Jul 00:00
Arrived at Indian port
29 Jul 00:00

Delay reasons

19 days of slip across 5 stages. A stage can have more than one reason.

  • Supplier delay at origin1d · Loaded at Origin

    Cargo aboard, Bill of Lading issued — behind plan

  • Weather on the voyage2d · At Sea

    Sailing from China or Australia to India — weather

  • Barge transfer wait2d · At Indian Port

    Arrived, unloading — includes barge transfer where the port is shallow — behind plan

  • Customs assessment queue7d · Customs Cleared

    Bill of Entry assessed, duty paid, cargo released — clearance queue

  • Truck shortage7d · Road to Plant

    Trucks moving from port to the factory — truck shortage

Voyage

Loading map…

Stages

  1. Order ConfirmedPlanned 28 Jun 2026 · Actual 28 Jun 2026

    Owner: Procurement. Purchase order placed with the supplier

    • Purchase order placed28 Jun 2026
  2. Vessel AssignedPlanned 29 Jun 2026 · Actual 29 Jun 2026

    Owner: Supplier. Supplier has named the ship and we have accepted it

    • Vessel named29 Jun 2026
  3. Loaded at OriginPlanned 09 Jul 2026 · Actual 10 Jul 2026 · 1 day late
    Supplier delay at origin · 1d

    Owner: Supplier. Cargo aboard, Bill of Lading issued — behind plan

    • Bill of LadingVerified
    • Commercial invoiceVerified
    • Certificate of originVerified
    • Loading finished10 Jul 2026
    • Bill of Lading issued10 Jul 2026
  4. At SeaPlanned 13 Jul 2026 · Actual 15 Jul 2026 · 2 days late
    Weather on the voyage · 2d

    Owner: Shipping line. Sailing from China or Australia to India — weather

    • Sailed15 Jul 2026
  5. At Indian PortPlanned 27 Jul 2026 · Actual 29 Jul 2026 · 2 days late
    Barge transfer wait · 2d

    Owner: Port operations. Arrived, unloading — includes barge transfer where the port is shallow — behind plan

    • Arrived at Indian port29 Jul 2026
  6. Customs ClearedPlanned 05 Aug 2026 · Actual 12 Aug 2026 · 7 days late
    Customs assessment queue · 7d

    Owner: Customs agent. Bill of Entry assessed, duty paid, cargo released — clearance queue

    • Bill of EntryVerified
    • Customs cleared12 Aug 2026
  7. Road to PlantPlanned 08 Aug 2026 · Actual 15 Aug 2026 · 7 days late
    Truck shortage · 7d

    Owner: Transporter. Trucks moving from port to the factory — truck shortage

    • E-way billVerified
    • First truck dispatched15 Aug 2026
  8. Received at PlantPlanned 20 Aug 2026 · Actual —

    Owner: Plant stores. Weighed in, plant receipt raised

    • Plant receiptExpected