Order Confirmed · 28 Jun 2026Order Confirmed28 Jun 2026Vessel Assigned · 29 Jun 2026Vessel Assigned29 Jun 2026Loaded at Origin · 10 Jul 2026Loaded at Origin10 Jul 2026+1dAt Sea · 15 Jul 2026At Sea15 Jul 2026+2dAt Indian Port · 29 Jul 2026At Indian Port29 Jul 2026+2dCustoms Cleared · 12 Aug 2026Customs Cleared12 Aug 2026+7dRoad to Plant · 15 Aug 2026Road to Plant15 Aug 2026+7dReceived at Plant · planned 20 Aug 2026Received at Plant20 Aug 2026

Road to Plant

7 days past plan

Trucks moving from port to the factory — truck shortage

Next: Received at Plant · Jamuria

Trucks on the road

2 of 5 trucks on the road

E-way bill issued on 5 trucks. 3 received at the plant.

Destination Jamuria.

Pricing

LineBasis₹/MTAmount% of cost
Material₹28₹10.89 L88.82%
Material valuePer shipment₹28₹10.89 L88.82%
Freight and port₹2₹65,9725.38%
Ocean freightPer shipment₹1₹43,5463.55%
Barge transferPer shipment₹0₹13,0641.07%
Port duesPer shipment₹0₹6,5320.53%
Port storage chargesPer shipment₹0₹2,8300.23%
Duty₹1₹27,2162.22%
Basic customs dutyPer shipment₹1₹27,2162.22%
Road₹1₹43,8183.58%
Road freightPer shipment₹1₹43,8183.58%
Total₹32₹12.26 L100.00%

IGST — recoverable

Shown separately because it is claimed back and does not sit in delivered cost.

₹54,432