IMP-2026-0500

Met Coke · 63,140.470 MT

Bowen Basin Carbon Pty Ltd · Hay Point → Haldia → Jamuria · MV Ocean Sentinel

Order Confirmed · 22 Jun 2025Order Confirmed22 Jun 2025Vessel Assigned · 24 Jun 2025Vessel Assigned24 Jun 2025+1dLoaded at Origin · 04 Jul 2025Loaded at Origin04 Jul 2025+1dAt Sea · 08 Jul 2025At Sea08 Jul 2025+1dAt Indian Port · 27 Jul 2025At Indian Port27 Jul 2025+1dCustoms Cleared · 11 Aug 2025Customs Cleared11 Aug 2025+7dRoad to Plant · 14 Aug 2025Road to Plant14 Aug 2025+7dReceived at Plant · 28 Aug 2025Received at Plant28 Aug 2025+9d

Quantity received against shipped

63,137.720 MT / 63,140.470 MT

Shortfall 2.750 MT · ₹84

Each leg's loss is valued at the cost accrued to that point.

Delivered cost per tonne

₹32.00

Budget ₹33.00 · −₹1.00

This journey

Hay Point → Haldia → Jamuria

Vessel
MV Ocean Sentinel
Bill of Lading
BL/0500/2026
Sailed
08 Jul 00:00
Arrived at Indian port
27 Jul 00:00

Delay reasons

27 days of slip across 7 stages. A stage can have more than one reason.

  • Vessel named late1d · Vessel Assigned

    Supplier has named the ship and we have accepted it — behind plan

  • Supplier delay at origin1d · Loaded at Origin

    Cargo aboard, Bill of Lading issued — behind plan

  • Weather on the voyage1d · At Sea

    Sailing from China or Australia to India — weather

  • Barge transfer wait1d · At Indian Port

    Arrived, unloading — includes barge transfer where the port is shallow — behind plan

  • Customs assessment queue7d · Customs Cleared

    Bill of Entry assessed, duty paid, cargo released — clearance queue

  • Truck shortage7d · Road to Plant

    Trucks moving from port to the factory — truck shortage

  • Road traffic9d · Received at Plant

    Weighed in, plant receipt raised — behind plan

Voyage

Loading map…

Stages

  1. Order ConfirmedPlanned 22 Jun 2025 · Actual 22 Jun 2025

    Owner: Procurement. Purchase order placed with the supplier

    • Purchase order placed22 Jun 2025
  2. Vessel AssignedPlanned 23 Jun 2025 · Actual 24 Jun 2025 · 1 day late
    Vessel named late · 1d

    Owner: Supplier. Supplier has named the ship and we have accepted it — behind plan

    • Vessel named24 Jun 2025
  3. Loaded at OriginPlanned 03 Jul 2025 · Actual 04 Jul 2025 · 1 day late
    Supplier delay at origin · 1d

    Owner: Supplier. Cargo aboard, Bill of Lading issued — behind plan

    • Bill of LadingVerified
    • Commercial invoiceVerified
    • Certificate of originVerified
    • Loading finished04 Jul 2025
    • Bill of Lading issued04 Jul 2025
  4. At SeaPlanned 07 Jul 2025 · Actual 08 Jul 2025 · 1 day late
    Weather on the voyage · 1d

    Owner: Shipping line. Sailing from China or Australia to India — weather

    • Sailed08 Jul 2025
  5. At Indian PortPlanned 26 Jul 2025 · Actual 27 Jul 2025 · 1 day late
    Barge transfer wait · 1d

    Owner: Port operations. Arrived, unloading — includes barge transfer where the port is shallow — behind plan

    • Arrived at Indian port27 Jul 2025
  6. Customs ClearedPlanned 04 Aug 2025 · Actual 11 Aug 2025 · 7 days late
    Customs assessment queue · 7d

    Owner: Customs agent. Bill of Entry assessed, duty paid, cargo released — clearance queue

    • Bill of EntryVerified
    • Customs cleared11 Aug 2025
  7. Road to PlantPlanned 07 Aug 2025 · Actual 14 Aug 2025 · 7 days late
    Truck shortage · 7d

    Owner: Transporter. Trucks moving from port to the factory — truck shortage

    • E-way billVerified
    • First truck dispatched14 Aug 2025
  8. Received at PlantPlanned 19 Aug 2025 · Actual 28 Aug 2025 · 9 days late
    Road traffic · 9d

    Owner: Plant stores. Weighed in, plant receipt raised — behind plan

    • Plant receiptVerified
    • Plant receipt raised28 Aug 2025