Tour

IMP-2026-0501

Coking Coal · 45,396.930 MT

Jiangsu Hengrui Resources Co. Ltd · Rizhao → Paradip → Sambalpur · MV Eastern Dawn

Order Confirmed · 31 Jul 2025Order Confirmed31 Jul 2025Vessel Assigned · 01 Aug 2025Vessel Assigned01 Aug 2025Loaded at Origin · 12 Aug 2025Loaded at Origin12 Aug 2025+1dAt Sea · 16 Aug 2025At Sea16 Aug 2025+1dAt Indian Port · 30 Aug 2025At Indian Port30 Aug 2025+1dCustoms Cleared · 08 Sep 2025Customs Cleared08 Sep 2025+1dRoad to Plant · 11 Sep 2025Road to Plant11 Sep 2025+1dReceived at Plant · 24 Sep 2025Received at Plant24 Sep 2025+2d

Quantity received against shipped

45,394.050 MT / 45,396.930 MT

Shortfall 2.880 MT · ₹85

Each leg's loss is valued at the cost accrued to that point.

Delivered cost per tonne

₹31.00

Budget ₹31.00 · +₹0.00

This journey

Rizhao → Paradip → Sambalpur

Vessel
MV Eastern Dawn
Bill of Lading
BL/0501/2026
Sailed
16 Aug 00:00
Arrived at Indian port
30 Aug 00:00

Delay reasons

7 days of slip across 6 stages. A stage can have more than one reason.

  • Supplier delay at origin1d · Loaded at Origin

    Cargo aboard, Bill of Lading issued — behind plan

  • Weather on the voyage1d · At Sea

    Sailing from China or Australia to India — weather

  • Barge transfer wait1d · At Indian Port

    Arrived, unloading — includes barge transfer where the port is shallow — behind plan

  • Customs assessment queue1d · Customs Cleared

    Bill of Entry assessed, duty paid, cargo released — clearance queue

  • Truck shortage1d · Road to Plant

    Trucks moving from port to the factory — truck shortage

  • Road traffic2d · Received at Plant

    Weighed in, plant receipt raised — behind plan

Voyage

Loading map…

Stages

  1. Order ConfirmedPlanned 31 Jul 2025 · Actual 31 Jul 2025

    Owner: Procurement. Purchase order placed with the supplier

    • Purchase order placed31 Jul 2025
  2. Vessel AssignedPlanned 01 Aug 2025 · Actual 01 Aug 2025

    Owner: Supplier. Supplier has named the ship and we have accepted it

    • Vessel named01 Aug 2025
  3. Loaded at OriginPlanned 11 Aug 2025 · Actual 12 Aug 2025 · 1 day late
    Supplier delay at origin · 1d

    Owner: Supplier. Cargo aboard, Bill of Lading issued — behind plan

    • Bill of LadingVerified
    • Commercial invoiceVerified
    • Certificate of originVerified
    • Loading finished12 Aug 2025
    • Bill of Lading issued12 Aug 2025
  4. At SeaPlanned 15 Aug 2025 · Actual 16 Aug 2025 · 1 day late
    Weather on the voyage · 1d

    Owner: Shipping line. Sailing from China or Australia to India — weather

    • Sailed16 Aug 2025
  5. At Indian PortPlanned 29 Aug 2025 · Actual 30 Aug 2025 · 1 day late
    Barge transfer wait · 1d

    Owner: Port operations. Arrived, unloading — includes barge transfer where the port is shallow — behind plan

    • Arrived at Indian port30 Aug 2025
  6. Customs ClearedPlanned 07 Sep 2025 · Actual 08 Sep 2025 · 1 day late
    Customs assessment queue · 1d

    Owner: Customs agent. Bill of Entry assessed, duty paid, cargo released — clearance queue

    • Bill of EntryVerified
    • Customs cleared08 Sep 2025
  7. Road to PlantPlanned 10 Sep 2025 · Actual 11 Sep 2025 · 1 day late
    Truck shortage · 1d

    Owner: Transporter. Trucks moving from port to the factory — truck shortage

    • E-way billVerified
    • First truck dispatched11 Sep 2025
  8. Received at PlantPlanned 22 Sep 2025 · Actual 24 Sep 2025 · 2 days late
    Road traffic · 2d

    Owner: Plant stores. Weighed in, plant receipt raised — behind plan

    • Plant receiptVerified
    • Plant receipt raised24 Sep 2025