IMP-2026-0501
Coking Coal · 45,396.930 MT
Jiangsu Hengrui Resources Co. Ltd · Rizhao → Paradip → Sambalpur · MV Eastern Dawn
Quantity received against shipped
45,394.050 MT / 45,396.930 MT
Shortfall 2.880 MT · ₹85
Each leg's loss is valued at the cost accrued to that point.
Delivered cost per tonne
₹31.00
Budget ₹31.00 · +₹0.00
This journey
Rizhao → Paradip → Sambalpur
- Vessel
- MV Eastern Dawn
- Bill of Lading
- BL/0501/2026
- Sailed
- 16 Aug 00:00
- Arrived at Indian port
- 30 Aug 00:00
Delay reasons
7 days of slip across 6 stages. A stage can have more than one reason.
- Supplier delay at origin1d · Loaded at Origin
Cargo aboard, Bill of Lading issued — behind plan
- Weather on the voyage1d · At Sea
Sailing from China or Australia to India — weather
- Barge transfer wait1d · At Indian Port
Arrived, unloading — includes barge transfer where the port is shallow — behind plan
- Customs assessment queue1d · Customs Cleared
Bill of Entry assessed, duty paid, cargo released — clearance queue
- Truck shortage1d · Road to Plant
Trucks moving from port to the factory — truck shortage
- Road traffic2d · Received at Plant
Weighed in, plant receipt raised — behind plan
Voyage
Stages
Order ConfirmedPlanned 31 Jul 2025 · Actual 31 Jul 2025
Owner: Procurement. Purchase order placed with the supplier
- Purchase order placed31 Jul 2025
Vessel AssignedPlanned 01 Aug 2025 · Actual 01 Aug 2025
Owner: Supplier. Supplier has named the ship and we have accepted it
- Vessel named01 Aug 2025
Loaded at OriginPlanned 11 Aug 2025 · Actual 12 Aug 2025 · 1 day late
Supplier delay at origin · 1dOwner: Supplier. Cargo aboard, Bill of Lading issued — behind plan
- Bill of LadingVerified
- Commercial invoiceVerified
- Certificate of originVerified
- Loading finished12 Aug 2025
- Bill of Lading issued12 Aug 2025
At SeaPlanned 15 Aug 2025 · Actual 16 Aug 2025 · 1 day late
Weather on the voyage · 1dOwner: Shipping line. Sailing from China or Australia to India — weather
- Sailed16 Aug 2025
At Indian PortPlanned 29 Aug 2025 · Actual 30 Aug 2025 · 1 day late
Barge transfer wait · 1dOwner: Port operations. Arrived, unloading — includes barge transfer where the port is shallow — behind plan
- Arrived at Indian port30 Aug 2025
Customs ClearedPlanned 07 Sep 2025 · Actual 08 Sep 2025 · 1 day late
Customs assessment queue · 1dOwner: Customs agent. Bill of Entry assessed, duty paid, cargo released — clearance queue
- Bill of EntryVerified
- Customs cleared08 Sep 2025
Road to PlantPlanned 10 Sep 2025 · Actual 11 Sep 2025 · 1 day late
Truck shortage · 1dOwner: Transporter. Trucks moving from port to the factory — truck shortage
- E-way billVerified
- First truck dispatched11 Sep 2025
Received at PlantPlanned 22 Sep 2025 · Actual 24 Sep 2025 · 2 days late
Road traffic · 2dOwner: Plant stores. Weighed in, plant receipt raised — behind plan
- Plant receiptVerified
- Plant receipt raised24 Sep 2025