IMP-2026-0502

Manganese Ore · 142,989.990 MT

Hebei Metallurgical Trading Co. Ltd · Lianyungang → Haldia → Jamuria · MV Cape Resolve

Order Confirmed · 27 Aug 2025Order Confirmed27 Aug 2025Vessel Assigned · 28 Aug 2025Vessel Assigned28 Aug 2025Loaded at Origin · 06 Sep 2025Loaded at Origin06 Sep 2025At Sea · 10 Sep 2025At Sea10 Sep 2025At Indian Port · 24 Sep 2025At Indian Port24 Sep 2025Customs Cleared · 08 Oct 2025Customs Cleared08 Oct 2025+4dRoad to Plant · 10 Oct 2025Road to Plant10 Oct 2025+3dReceived at Plant · 21 Oct 2025Received at Plant21 Oct 2025+2d

Quantity received against shipped

142,986.980 MT / 142,989.990 MT

Shortfall 3.010 MT · ₹90

Each leg's loss is valued at the cost accrued to that point.

Delivered cost per tonne

₹31.00

Budget ₹31.00 · +₹0.00

This journey

Lianyungang → Haldia → Jamuria

Vessel
MV Cape Resolve
Bill of Lading
BL/0502/2026
Sailed
10 Sep 00:00
Arrived at Indian port
24 Sep 00:00

Delay reasons

9 days of slip across 3 stages. A stage can have more than one reason.

  • Customs assessment queue4d · Customs Cleared

    Bill of Entry assessed, duty paid, cargo released — clearance queue

  • Truck shortage3d · Road to Plant

    Trucks moving from port to the factory — truck shortage

  • Road traffic2d · Received at Plant

    Weighed in, plant receipt raised — behind plan

Voyage

Loading map…

Stages

  1. Order ConfirmedPlanned 27 Aug 2025 · Actual 27 Aug 2025

    Owner: Procurement. Purchase order placed with the supplier

    • Purchase order placed27 Aug 2025
  2. Vessel AssignedPlanned 28 Aug 2025 · Actual 28 Aug 2025

    Owner: Supplier. Supplier has named the ship and we have accepted it

    • Vessel named28 Aug 2025
  3. Loaded at OriginPlanned 07 Sep 2025 · Actual 06 Sep 2025 · 1 day early

    Owner: Supplier. Cargo aboard, Bill of Lading issued

    • Bill of LadingVerified
    • Commercial invoiceVerified
    • Certificate of originVerified
    • Loading finished06 Sep 2025
    • Bill of Lading issued06 Sep 2025
  4. At SeaPlanned 11 Sep 2025 · Actual 10 Sep 2025 · 1 day early

    Owner: Shipping line. Sailing from China or Australia to India

    • Sailed10 Sep 2025
  5. At Indian PortPlanned 25 Sep 2025 · Actual 24 Sep 2025 · 1 day early

    Owner: Port operations. Arrived, unloading — includes barge transfer where the port is shallow

    • Arrived at Indian port24 Sep 2025
  6. Customs ClearedPlanned 04 Oct 2025 · Actual 08 Oct 2025 · 4 days late
    Customs assessment queue · 4d

    Owner: Customs agent. Bill of Entry assessed, duty paid, cargo released — clearance queue

    • Bill of EntryVerified
    • Customs cleared08 Oct 2025
  7. Road to PlantPlanned 07 Oct 2025 · Actual 10 Oct 2025 · 3 days late
    Truck shortage · 3d

    Owner: Transporter. Trucks moving from port to the factory — truck shortage

    • E-way billVerified
    • First truck dispatched10 Oct 2025
  8. Received at PlantPlanned 19 Oct 2025 · Actual 21 Oct 2025 · 2 days late
    Road traffic · 2d

    Owner: Plant stores. Weighed in, plant receipt raised — behind plan

    • Plant receiptVerified
    • Plant receipt raised21 Oct 2025