IMP-2026-0502
Manganese Ore · 142,989.990 MT
Hebei Metallurgical Trading Co. Ltd · Lianyungang → Haldia → Jamuria · MV Cape Resolve
Quantity received against shipped
142,986.980 MT / 142,989.990 MT
Shortfall 3.010 MT · ₹90
Each leg's loss is valued at the cost accrued to that point.
Delivered cost per tonne
₹31.00
Budget ₹31.00 · +₹0.00
Pricing
| Line | Basis | ₹/MT | Amount | % of cost |
|---|---|---|---|---|
| Material | ₹28 | ₹40.04 L | 89.13% | |
| Material value | Per shipment | ₹28 | ₹40.04 L | 89.13% |
| Freight and port | ₹2 | ₹2.41 L | 5.36% | |
| Ocean freight | Per shipment | ₹1 | ₹1.60 L | 3.56% |
| Barge transfer | Per shipment | ₹0 | ₹48,045 | 1.07% |
| Port dues | Per shipment | ₹0 | ₹24,022 | 0.53% |
| Port storage charges | Per shipment | ₹0 | ₹8,808 | 0.20% |
| Duty | ₹1 | ₹1.00 L | 2.23% | |
| Basic customs duty | Per shipment | ₹1 | ₹1.00 L | 2.23% |
| Road | ₹1 | ₹1.47 L | 3.28% | |
| Road freight | Per shipment | ₹1 | ₹1.47 L | 3.28% |
| Total | ₹31 | ₹44.92 L | 100.00% | |
IGST — recoverable
Shown separately because it is claimed back and does not sit in delivered cost.
₹2.00 L