Demo date · 25 Aug 2026
Tour

IMP-2026-0505

Met Coke · 29,930.930 MT

Pilbara Bulk Minerals Pty Ltd · Port Hedland → Paradip → Sambalpur · MV River Falcon

Order Confirmed · 15 Nov 2025Order Confirmed15 Nov 2025Vessel Assigned · 17 Nov 2025Vessel Assigned17 Nov 2025+1dLoaded at Origin · 28 Nov 2025Loaded at Origin28 Nov 2025+2dAt Sea · 02 Dec 2025At Sea02 Dec 2025+2dAt Indian Port · 15 Dec 2025At Indian Port15 Dec 2025+2dCustoms Cleared · 23 Dec 2025Customs Cleared23 Dec 2025+1dRoad to Plant · 27 Dec 2025Road to Plant27 Dec 2025+2dReceived at Plant · 10 Jan 2026Received at Plant10 Jan 2026+4d

Quantity received against shipped

29,927.530 MT / 29,930.930 MT

Shortfall 3.400 MT · ₹103

Each leg's loss is valued at the cost accrued to that point.

Delivered cost per tonne

₹32.00

Budget ₹32.00 · +₹0.00

This journey

Port Hedland → Paradip → Sambalpur

Vessel
MV River Falcon
Bill of Lading
BL/0505/2026
Sailed
02 Dec 00:00
Arrived at Indian port
15 Dec 00:00

Delay reasons

14 days of slip across 7 stages. A stage can have more than one reason.

  • Vessel named late1d · Vessel Assigned

    Supplier has named the ship and we have accepted it — behind plan

  • Supplier delay at origin2d · Loaded at Origin

    Cargo aboard, Bill of Lading issued — behind plan

  • Weather on the voyage2d · At Sea

    Sailing from China or Australia to India — weather

  • Barge transfer wait2d · At Indian Port

    Arrived, unloading — includes barge transfer where the port is shallow — behind plan

  • Customs assessment queue1d · Customs Cleared

    Bill of Entry assessed, duty paid, cargo released — clearance queue

  • Truck shortage2d · Road to Plant

    Trucks moving from port to the factory — truck shortage

  • Road traffic4d · Received at Plant

    Weighed in, plant receipt raised — behind plan

Voyage

Loading map…

Stages

  1. Order ConfirmedPlanned 15 Nov 2025 · Actual 15 Nov 2025

    Owner: Procurement. Purchase order placed with the supplier

    • Purchase order placed15 Nov 2025
  2. Vessel AssignedPlanned 16 Nov 2025 · Actual 17 Nov 2025 · 1 day late
    Vessel named late · 1d

    Owner: Supplier. Supplier has named the ship and we have accepted it — behind plan

    • Vessel named17 Nov 2025
  3. Loaded at OriginPlanned 26 Nov 2025 · Actual 28 Nov 2025 · 2 days late
    Supplier delay at origin · 2d

    Owner: Supplier. Cargo aboard, Bill of Lading issued — behind plan

    • Bill of LadingVerified
    • Commercial invoiceVerified
    • Certificate of originVerified
    • Loading finished28 Nov 2025
    • Bill of Lading issued28 Nov 2025
  4. At SeaPlanned 30 Nov 2025 · Actual 02 Dec 2025 · 2 days late
    Weather on the voyage · 2d

    Owner: Shipping line. Sailing from China or Australia to India — weather

    • Sailed02 Dec 2025
  5. At Indian PortPlanned 13 Dec 2025 · Actual 15 Dec 2025 · 2 days late
    Barge transfer wait · 2d

    Owner: Port operations. Arrived, unloading — includes barge transfer where the port is shallow — behind plan

    • Arrived at Indian port15 Dec 2025
  6. Customs ClearedPlanned 22 Dec 2025 · Actual 23 Dec 2025 · 1 day late
    Customs assessment queue · 1d

    Owner: Customs agent. Bill of Entry assessed, duty paid, cargo released — clearance queue

    • Bill of EntryVerified
    • Customs cleared23 Dec 2025
  7. Road to PlantPlanned 25 Dec 2025 · Actual 27 Dec 2025 · 2 days late
    Truck shortage · 2d

    Owner: Transporter. Trucks moving from port to the factory — truck shortage

    • E-way billVerified
    • First truck dispatched27 Dec 2025
  8. Received at PlantPlanned 06 Jan 2026 · Actual 10 Jan 2026 · 4 days late
    Road traffic · 4d

    Owner: Plant stores. Weighed in, plant receipt raised — behind plan

    • Plant receiptVerified
    • Plant receipt raised10 Jan 2026