ShyamMetalics
powered by WhizCloud
Demo date · 25 Aug 2026
Tour

IMP-2026-0509

Limestone · 59,400.930 MT

Meridian Commodities Pte Ltd · Hay Point → Paradip → Sambalpur · MV Austral Wind

Order Confirmed · 27 Feb 2026Order Confirmed27 Feb 2026Vessel Assigned · 28 Feb 2026Vessel Assigned28 Feb 2026Loaded at Origin · 12 Mar 2026Loaded at Origin12 Mar 2026+2dAt Sea · 17 Mar 2026At Sea17 Mar 2026+3dAt Indian Port · 05 Apr 2026At Indian Port05 Apr 2026+3dCustoms Cleared · 14 Apr 2026Customs Cleared14 Apr 2026+3dRoad to Plant · 17 Apr 2026Road to Plant17 Apr 2026+3dReceived at Plant · 28 Apr 2026Received at Plant28 Apr 2026+2d

Quantity received against shipped

59,397.890 MT / 59,400.930 MT

Shortfall 3.040 MT · ₹91

Each leg's loss is valued at the cost accrued to that point.

Delivered cost per tonne

₹32.00

Budget ₹33.00 · −₹1.00

This journey

Hay Point → Paradip → Sambalpur

Vessel
MV Austral Wind
Bill of Lading
BL/0509/2026
Sailed
17 Mar 00:00
Arrived at Indian port
05 Apr 00:00

Delay reasons

16 days of slip across 6 stages. A stage can have more than one reason.

  • Supplier delay at origin2d · Loaded at Origin

    Cargo aboard, Bill of Lading issued — behind plan

  • Weather on the voyage3d · At Sea

    Sailing from China or Australia to India — weather

  • Barge transfer wait3d · At Indian Port

    Arrived, unloading — includes barge transfer where the port is shallow — behind plan

  • Customs assessment queue3d · Customs Cleared

    Bill of Entry assessed, duty paid, cargo released — clearance queue

  • Truck shortage3d · Road to Plant

    Trucks moving from port to the factory — truck shortage

  • Road traffic2d · Received at Plant

    Weighed in, plant receipt raised — behind plan

Voyage

Loading map…

Stages

  1. Order ConfirmedPlanned 27 Feb 2026 · Actual 27 Feb 2026

    Owner: Procurement. Purchase order placed with the supplier

    • Purchase order placed27 Feb 2026
  2. Vessel AssignedPlanned 28 Feb 2026 · Actual 28 Feb 2026

    Owner: Supplier. Supplier has named the ship and we have accepted it

    • Vessel named28 Feb 2026
  3. Loaded at OriginPlanned 10 Mar 2026 · Actual 12 Mar 2026 · 2 days late
    Supplier delay at origin · 2d

    Owner: Supplier. Cargo aboard, Bill of Lading issued — behind plan

    • Bill of LadingVerified
    • Commercial invoiceVerified
    • Certificate of originVerified
    • Loading finished12 Mar 2026
    • Bill of Lading issued12 Mar 2026
  4. At SeaPlanned 14 Mar 2026 · Actual 17 Mar 2026 · 3 days late
    Weather on the voyage · 3d

    Owner: Shipping line. Sailing from China or Australia to India — weather

    • Sailed17 Mar 2026
  5. At Indian PortPlanned 02 Apr 2026 · Actual 05 Apr 2026 · 3 days late
    Barge transfer wait · 3d

    Owner: Port operations. Arrived, unloading — includes barge transfer where the port is shallow — behind plan

    • Arrived at Indian port05 Apr 2026
  6. Customs ClearedPlanned 11 Apr 2026 · Actual 14 Apr 2026 · 3 days late
    Customs assessment queue · 3d

    Owner: Customs agent. Bill of Entry assessed, duty paid, cargo released — clearance queue

    • Bill of EntryVerified
    • Customs cleared14 Apr 2026
  7. Road to PlantPlanned 14 Apr 2026 · Actual 17 Apr 2026 · 3 days late
    Truck shortage · 3d

    Owner: Transporter. Trucks moving from port to the factory — truck shortage

    • E-way billVerified
    • First truck dispatched17 Apr 2026
  8. Received at PlantPlanned 26 Apr 2026 · Actual 28 Apr 2026 · 2 days late
    Road traffic · 2d

    Owner: Plant stores. Weighed in, plant receipt raised — behind plan

    • Plant receiptVerified
    • Plant receipt raised28 Apr 2026