ANCHORLINE
Demo date · 20 Aug 2026
What am I looking at?

What one tonne of this material actually cost by the time it was standing in the plant yard. The waterfall builds it up from the price we paid the seller, through freight, port handling, duty, demurrage and road transport. It is compared against what was budgeted, and the difference is explained line by line. Quantity shortfall comes first in that explanation because it changes the denominator every other line is divided by.

Per tonne, estimated and actual
Total cost divided by the quantity that actually arrived at the plant, not by what was shipped.
Variance
Actual against budget, in rupees per tonne and as a percentage. Positive means it cost more than planned.
Recoverable
IGST. Paid in cash but reclaimed, so it is shown separately and kept out of the cost per tonne.
Memo
The value of material lost in transit. It is not an extra invoice; it is already reflected in the fact that fewer tonnes carry the same spend.

Read the full guide for this screen · written for Commercial and finance

PCL-2026-0525

Coking Coal Hard · 36,250.000 MT · CFR Haldia · MV Southern Cross (IMO 9712454) · B/L BL/0525 dated 11 Aug 2025

Estimated per tonne

₹28,481.00

Actual per tonne

₹29,505.00

Variance per tonne

+₹1,024.00

3.59 % against estimate

Parcel total

₹1,05,99,13,587.79

+₹3,67,59,834.05 against estimate

Per-tonne figures divide by 35,923.750 MT Goods receipt note at the plant.

How the tonne is built

Each bar adds to the one before it. The final bar is the landed cost of one tonne of material standing in the plant yard.

Loading chart…

What moved the number

Ranked by rupees per tonne. Quantity shortfall comes first because it changes the denominator every other line is divided by.

  1. 1. Quantity shortfall+₹266.00 / MT

    326.25 MT of the Bill of Lading quantity never reached the plant. The same spend is now divided over fewer tonnes, so every remaining tonne carries more.

  2. 2. Goods value+₹620.00 / MT

    Budgeted ₹24,240/MT, came in at ₹24,860/MT.

  3. 3. Ocean & lighterage+₹193.00 / MT

    Budgeted ₹1,855/MT, came in at ₹2,048/MT.

  4. 4. Port & handling+₹109.00 / MT

    Budgeted ₹1,016/MT, came in at ₹1,125/MT.

  5. 5. Demurrage+₹52.00 / MT

    Nothing was budgeted for this. It is entirely an overrun.

  6. 6. Inland+₹31.00 / MT

    Budgeted ₹689/MT, came in at ₹720/MT.

Cost lines

Grouped into the buckets used by the waterfall. Open a bucket to see the individual estimated and actual lines behind it.

Goods value84.3 % of totalest ₹24,240.00/MTact ₹24,860.00/MT+₹620.00/MT
LineNatureCounterpartyIncurredPer tonneAmount
Goods valueACT/0525/02ActualBowen Basin Carbon Pty Ltd30 Sep 2025 00:00 +05:30₹24,860.00₹89,30,64,425.00
Goods valueEstimatedBowen Basin Carbon Pty Ltd11 Aug 2025 00:00 +05:30₹24,240.00₹87,07,91,700.00
Ocean & lighterage6.9 % of totalest ₹1,855.00/MTact ₹2,048.00/MT+₹193.00/MT
LineNatureCounterpartyIncurredPer tonneAmount
Marine insuranceACT/0525/04ActualThe New India Assurance Co. Ltd30 Sep 2025 00:00 +05:30₹119.00₹42,74,926.25
LighterageACT/0525/06ActualHooghly Floating Cranes Pvt Ltd30 Sep 2025 00:00 +05:30₹1,080.00₹3,87,97,650.00
Floating craneACT/0525/08ActualHooghly Floating Cranes Pvt Ltd30 Sep 2025 00:00 +05:30₹465.00₹1,67,04,543.75
Barge freightACT/0525/10ActualHooghly Floating Cranes Pvt Ltd30 Sep 2025 00:00 +05:30₹384.00₹1,37,94,720.00
Marine insuranceEstimatedThe New India Assurance Co. Ltd11 Aug 2025 00:00 +05:30₹115.00₹41,31,231.25
LighterageEstimatedHooghly Floating Cranes Pvt Ltd11 Aug 2025 00:00 +05:30₹960.00₹3,44,86,800.00
Floating craneEstimatedHooghly Floating Cranes Pvt Ltd11 Aug 2025 00:00 +05:30₹410.00₹1,47,28,737.50
Barge freightEstimatedHooghly Floating Cranes Pvt Ltd11 Aug 2025 00:00 +05:30₹370.00₹1,32,91,787.50
Port & handling3.8 % of totalest ₹1,016.00/MTact ₹1,125.00/MT+₹109.00/MT
LineNatureCounterpartyIncurredPer tonneAmount
Port duesACT/0525/12ActualEastport Shipping Agency30 Sep 2025 00:00 +05:30₹212.00₹76,15,835.00
WharfageACT/0525/14ActualEastport Shipping Agency30 Sep 2025 00:00 +05:30₹158.00₹56,75,952.50
StevedoringACT/0525/16ActualBengal Stevedores Company30 Sep 2025 00:00 +05:30₹506.00₹1,81,77,417.50
Plot rentACT/0525/18ActualEastport Shipping Agency30 Sep 2025 00:00 +05:30₹139.00₹49,93,401.25
Customs house agent feeACT/0525/20ActualBengal Clearing & Forwarding Pvt Ltd30 Sep 2025 00:00 +05:30₹34.00₹12,21,407.50
Survey feeACT/0525/22ActualSGS India Pvt Ltd30 Sep 2025 00:00 +05:30₹47.00₹16,88,416.25
DocumentationACT/0525/24ActualBengal Clearing & Forwarding Pvt Ltd30 Sep 2025 00:00 +05:30₹29.00₹10,41,788.75
Port duesEstimatedEastport Shipping Agency11 Aug 2025 00:00 +05:30₹205.00₹73,64,368.75
WharfageEstimatedEastport Shipping Agency11 Aug 2025 00:00 +05:30₹158.00₹56,75,952.50
StevedoringEstimatedBengal Stevedores Company11 Aug 2025 00:00 +05:30₹470.00₹1,68,84,162.50
Plot rentEstimatedEastport Shipping Agency11 Aug 2025 00:00 +05:30₹88.00₹31,61,290.00
Customs house agent feeEstimatedBengal Clearing & Forwarding Pvt Ltd11 Aug 2025 00:00 +05:30₹34.00₹12,21,407.50
Survey feeEstimatedSGS India Pvt Ltd11 Aug 2025 00:00 +05:30₹41.00₹14,72,873.75
DocumentationEstimatedBengal Clearing & Forwarding Pvt Ltd11 Aug 2025 00:00 +05:30₹20.00₹7,18,475.00
Duties2.3 % of totalest ₹670.00/MTact ₹687.00/MT+₹17.00/MT
LineNatureCounterpartyIncurredPer tonneAmount
Basic Customs DutyACT/0525/32ActualBengal Clearing & Forwarding Pvt Ltd30 Sep 2025 00:00 +05:30₹624.00₹2,24,33,483.78
Social Welfare SurchargeACT/0525/34ActualBengal Clearing & Forwarding Pvt Ltd30 Sep 2025 00:00 +05:30₹62.00₹22,43,348.38
Basic Customs DutyEstimatedBengal Clearing & Forwarding Pvt Ltd11 Aug 2025 00:00 +05:30₹609.00₹2,18,73,073.28
Social Welfare SurchargeEstimatedBengal Clearing & Forwarding Pvt Ltd11 Aug 2025 00:00 +05:30₹61.00₹21,87,307.33
Demurrage0.2 % of totalest ₹0.00/MTact ₹52.00/MT+₹52.00/MT
LineNatureCounterpartyIncurredPer tonneAmount
DemurrageDisputedACT/0525/36AccruedBowen Basin Carbon Pty Ltd11 Oct 2025 00:00 +05:30₹52.00₹18,72,125.00
Inland2.4 % of totalest ₹689.00/MTact ₹720.00/MT+₹31.00/MT
LineNatureCounterpartyIncurredPer tonneAmount
Road freightACT/0525/26ActualEastern Haulage Logistics30 Sep 2025 00:00 +05:30₹638.00₹2,29,19,352.50
Plant handlingACT/0525/28ActualInternal30 Sep 2025 00:00 +05:30₹82.00₹29,27,785.63
Road freightEstimatedEastern Haulage Logistics11 Aug 2025 00:00 +05:30₹610.00₹2,19,13,487.50
Plant handlingEstimatedInternal11 Aug 2025 00:00 +05:30₹79.00₹28,37,976.25
Finance & other0.0 % of totalest ₹12.00/MTact ₹13.00/MT+₹1.00/MT
LineNatureCounterpartyIncurredPer tonneAmount
Bank chargesACT/0525/30ActualState Bank of India30 Sep 2025 00:00 +05:30₹13.00₹4,67,008.75
Bank chargesEstimatedState Bank of India11 Aug 2025 00:00 +05:30₹12.00₹4,13,123.13

Outside the cost per tonne

Recoverable — input tax credit, not cost

₹4,61,00,809.17

Integrated GST paid at the border is claimed back as input tax credit against output GST. It leaves the bank account but never lands on the cost of the material, so it is excluded from every per-tonne figure above.

  • Integrated GST · ₹4,61,00,809.17 · ₹1,283.00/MT

Memo — value of material lost, already reflected in the per-tonne denominator

₹81,10,575.00

The rupee value of the material that never arrived. Adding it to the cost total would count the loss twice, because the tonnes it represents have already been removed from the denominator.

  • Transit loss · ₹81,10,575.00