The contract gives us a fixed number of hours to unload the ship, free of charge. Run past it and the shipowner charges demurrage for every day over. This screen recalculates that time from the Statement of Facts, event by event, and puts our number next to the seller's claim. Where the two differ, the reason is a specific event whose treatment we dispute — usually rain or waiting for barges.

Allowed
Cargo quantity divided by the contractual discharge rate. If the contract says 8,000 tonnes a day and the cargo is 45,000 tonnes, we get 135 hours.
Used
Time actually consumed, after excepted periods are stripped out. Sundays, holidays and weather come out if the contract says they do.
Claimed against computed
What the seller says we owe, against what the same events give when the contract is applied strictly. The gap is what a rebuttal is worth.
Rebuttal window
The days left to dispute the claim. Miss it and the claim is deemed accepted in full, whatever the facts say.

Read the full guide for this screen · written for The laytime analyst

PCL-2026-0535

Manganese Ore · 38,750.000 MT · CFR Haldia · MV Pacific Noble (IMO 9762003) · B/L BL/0535 dated 08 May 2026

Seller claims
$26,250.00
42.000 h on dem.
Our position
$21,250.00
34.000 h on dem.
In dispute
$5,000.00
8.000 h

Laytime ribbon

One cell per hour from commencement to completion. Hover for the governing event; click to open the evidence document panel.

17 Jun18 Jun19 Jun20 Jun21 Jun22 Jun23 Jun24 Jun25 JunDEMURRAGE BEGINS · 23 Jun 2026 16:45
  • Counts
  • Excepted
  • Disputed exception
  • On demurrage

Exception ledger

Disputed total 8.000 h

FromToHoursReasonContract basisEvidenceBuyerSellerDisputed
18 Jun 2026 12:30 +05:3019 Jun 2026 12:30 +05:3024.000 hSunday — SHEXrateBasis SHEXSOF/0535ExceptedAgreedNo
20 Jun 2026 06:30 +05:3020 Jun 2026 14:30 +05:308.000 hWeather stoppageweatherStoppagesCount = falseSOF/0535ExceptedSeller counts the stoppage in full — rain recorded but cargo work continued.Yes

Rebuttal

Deadline 07 Aug 2026 00:00 +05:30
14d overdueStatus SETTLED

Statement moved to REBUTTED. Reset demo to restore the seed state.