Demo date · 25 Aug 2026
Tour

IMP-2026-0431

Coking Coal · 45,511.210 MT

Pilbara Bulk Minerals Pty Ltd · Port Hedland → Paradip → Sambalpur · MV Mineral Quest

Order Confirmed · 20 Jul 2026Order Confirmed20 Jul 2026Vessel Assigned · 22 Jul 2026Vessel Assigned22 Jul 2026+1dLoaded at Origin · 02 Aug 2026Loaded at Origin02 Aug 2026+2dAt Sea · 06 Aug 2026At Sea06 Aug 2026+2dAt Indian Port · 20 Aug 2026At Indian Port20 Aug 2026+3dCustoms Cleared · planned 26 Aug 2026Customs Cleared26 Aug 2026Road to Plant · planned 29 Aug 2026Road to Plant29 Aug 2026Received at Plant · planned 10 Sep 2026Received at Plant10 Sep 2026

At Indian Port

3 days past plan

Arrived, unloading — includes barge transfer where the port is shallow — behind plan

Next: Customs Cleared

Unloaded against shipped

45,510.110 MT / 45,511.210 MT

Survey gap 1.100 MT — cargo still in the pipeline, not a plant shortfall.

This journey

Port Hedland → Paradip → Sambalpur

Vessel
MV Mineral Quest
Bill of Lading
BL/0431/2026
Sailed
06 Aug 00:00
Arrived at Indian port
20 Aug 00:00

Delay reasons

8 days of slip across 4 stages. A stage can have more than one reason.

  • Vessel named late1d · Vessel Assigned

    Supplier has named the ship and we have accepted it — behind plan

  • Supplier delay at origin2d · Loaded at Origin

    Cargo aboard, Bill of Lading issued — behind plan

  • Weather on the voyage2d · At Sea

    Sailing from China or Australia to India — weather

  • Barge transfer wait3d · At Indian Port

    Arrived, unloading — includes barge transfer where the port is shallow — behind plan

Voyage

Loading map…

Stages

  1. Order ConfirmedPlanned 20 Jul 2026 · Actual 20 Jul 2026

    Owner: Procurement. Purchase order placed with the supplier

    • Purchase order placed20 Jul 2026
  2. Vessel AssignedPlanned 21 Jul 2026 · Actual 22 Jul 2026 · 1 day late
    Vessel named late · 1d

    Owner: Supplier. Supplier has named the ship and we have accepted it — behind plan

    • Vessel named22 Jul 2026
  3. Loaded at OriginPlanned 31 Jul 2026 · Actual 02 Aug 2026 · 2 days late
    Supplier delay at origin · 2d

    Owner: Supplier. Cargo aboard, Bill of Lading issued — behind plan

    • Bill of LadingVerified
    • Commercial invoiceVerified
    • Certificate of originVerified
    • Loading finished02 Aug 2026
    • Bill of Lading issued02 Aug 2026
  4. At SeaPlanned 04 Aug 2026 · Actual 06 Aug 2026 · 2 days late
    Weather on the voyage · 2d

    Owner: Shipping line. Sailing from China or Australia to India — weather

    • Sailed06 Aug 2026
  5. At Indian PortPlanned 17 Aug 2026 · Actual 20 Aug 2026 · 3 days late
    Barge transfer wait · 3d

    Owner: Port operations. Arrived, unloading — includes barge transfer where the port is shallow — behind plan

    • Arrived at Indian port20 Aug 2026
  6. Customs ClearedPlanned 26 Aug 2026 · Actual —

    Owner: Customs agent. Bill of Entry assessed, duty paid, cargo released

    • Bill of EntryExpected
  7. Road to PlantPlanned 29 Aug 2026 · Actual —

    Owner: Transporter. Trucks moving from port to the factory

    • E-way billExpected
  8. Received at PlantPlanned 10 Sep 2026 · Actual —

    Owner: Plant stores. Weighed in, plant receipt raised

    • Plant receiptExpected