ShyamMetalics
powered by WhizCloud
Demo date · 25 Aug 2026
Tour

IMP-2026-0431

Coking Coal · 45,511.210 MT

Pilbara Bulk Minerals Pty Ltd · Port Hedland → Paradip → Sambalpur · MV Mineral Quest

Order Confirmed · 20 Jul 2026Order Confirmed20 Jul 2026Vessel Assigned · 22 Jul 2026Vessel Assigned22 Jul 2026+1dLoaded at Origin · 02 Aug 2026Loaded at Origin02 Aug 2026+2dAt Sea · 06 Aug 2026At Sea06 Aug 2026+2dAt Indian Port · 20 Aug 2026At Indian Port20 Aug 2026+3dCustoms Cleared · planned 26 Aug 2026Customs Cleared26 Aug 2026Road to Plant · planned 29 Aug 2026Road to Plant29 Aug 2026Received at Plant · planned 10 Sep 2026Received at Plant10 Sep 2026

At Indian Port

3 days past plan

Arrived, unloading — includes barge transfer where the port is shallow — behind plan

Next: Customs Cleared

Unloaded against shipped

45,510.110 MT / 45,511.210 MT

Survey gap 1.100 MT — cargo still in the pipeline, not a plant shortfall.

Checklist by stage

Loaded at Origin

  • Bill of LadingVerified
  • Commercial invoiceVerified
  • Certificate of originVerified

Customs Cleared

Road to Plant

Received at Plant

  • Plant receiptExpected

Customs

No Bill of Entry filed yet.