Coking Coal · 45,511.210 MT

Pilbara Bulk Minerals Pty Ltd · Port Hedland → Paradip → Sambalpur · MV Mineral Quest

Order Confirmed · 20 Jul 2026Order Confirmed20 Jul 2026Vessel Assigned · 22 Jul 2026Vessel Assigned22 Jul 2026+1dLoaded at Origin · 02 Aug 2026Loaded at Origin02 Aug 2026+2dAt Sea · 06 Aug 2026At Sea06 Aug 2026+2dAt Indian Port · 20 Aug 2026At Indian Port20 Aug 2026+3dCustoms Cleared · planned 26 Aug 2026Customs Cleared26 Aug 2026Road to Plant · planned 29 Aug 2026Road to Plant29 Aug 2026Received at Plant · planned 10 Sep 2026Received at Plant10 Sep 2026

At Indian Port

3 days past plan

Arrived, unloading — includes barge transfer where the port is shallow — behind plan

Next: Customs Cleared

Unloaded against shipped

45,510.110 MT / 45,511.210 MT

Survey gap 1.100 MT — cargo still in the pipeline, not a plant shortfall.

Pricing

LineBasis₹/MTAmount% of cost
Material₹28₹12.74 L90.25%
Material valuePer shipment₹28₹12.74 L90.25%
Freight and port₹1₹61,1674.33%
Ocean freightPer shipment₹1₹50,9733.61%
Port duesPer shipment₹0₹7,6460.54%
Port storage chargesPer shipment₹0₹2,5490.18%
Duty₹1₹31,8582.26%
Basic customs dutyPer shipment₹1₹31,8582.26%
Road₹1₹44,6013.16%
Road freightPer shipment₹1₹44,6013.16%
Total₹31₹14.12 L100.00%

IGST — recoverable

Shown separately because it is claimed back and does not sit in delivered cost.

₹63,716