IMP-2026-0431
Coking Coal · 45,511.210 MT
Pilbara Bulk Minerals Pty Ltd · Port Hedland → Paradip → Sambalpur · MV Mineral Quest
At Indian Port
3 days past plan
Arrived, unloading — includes barge transfer where the port is shallow — behind plan
Next: Customs Cleared
Unloaded against shipped
45,510.110 MT / 45,511.210 MT
Survey gap 1.100 MT — cargo still in the pipeline, not a plant shortfall.
Pricing
| Line | Basis | ₹/MT | Amount | % of cost |
|---|---|---|---|---|
| Material | ₹28 | ₹12.74 L | 90.25% | |
| Material value | Per shipment | ₹28 | ₹12.74 L | 90.25% |
| Freight and port | ₹1 | ₹61,167 | 4.33% | |
| Ocean freight | Per shipment | ₹1 | ₹50,973 | 3.61% |
| Port dues | Per shipment | ₹0 | ₹7,646 | 0.54% |
| Port storage charges | Per shipment | ₹0 | ₹2,549 | 0.18% |
| Duty | ₹1 | ₹31,858 | 2.26% | |
| Basic customs duty | Per shipment | ₹1 | ₹31,858 | 2.26% |
| Road | ₹1 | ₹44,601 | 3.16% | |
| Road freight | Per shipment | ₹1 | ₹44,601 | 3.16% |
| Total | ₹31 | ₹14.12 L | 100.00% | |
IGST — recoverable
Shown separately because it is claimed back and does not sit in delivered cost.
₹63,716