IMP-2026-0510

Met Coke · 43,623.990 MT

Rizhao Carbon Materials Co. Ltd · Rizhao → Haldia → Jamuria · MV Yellow River

Order Confirmed · 30 Mar 2026Order Confirmed30 Mar 2026Vessel Assigned · 31 Mar 2026Vessel Assigned31 Mar 2026Loaded at Origin · 11 Apr 2026Loaded at Origin11 Apr 2026+1dAt Sea · 16 Apr 2026At Sea16 Apr 2026+2dAt Indian Port · 30 Apr 2026At Indian Port30 Apr 2026+2dCustoms Cleared · 11 May 2026Customs Cleared11 May 2026+4dRoad to Plant · 14 May 2026Road to Plant14 May 2026+4dReceived at Plant · 25 May 2026Received at Plant25 May 2026+3d

Quantity received against shipped

43,621.670 MT / 43,623.990 MT

Shortfall 2.320 MT · ₹71

Each leg's loss is valued at the cost accrued to that point.

Delivered cost per tonne

₹32.00

Budget ₹32.00 · +₹0.00

This journey

Rizhao → Haldia → Jamuria

Vessel
MV Yellow River
Bill of Lading
BL/0510/2026
Sailed
16 Apr 00:00
Arrived at Indian port
30 Apr 00:00

Delay reasons

16 days of slip across 6 stages. A stage can have more than one reason.

  • Supplier delay at origin1d · Loaded at Origin

    Cargo aboard, Bill of Lading issued — behind plan

  • Weather on the voyage2d · At Sea

    Sailing from China or Australia to India — weather

  • Barge transfer wait2d · At Indian Port

    Arrived, unloading — includes barge transfer where the port is shallow — behind plan

  • Customs assessment queue4d · Customs Cleared

    Bill of Entry assessed, duty paid, cargo released — clearance queue

  • Truck shortage4d · Road to Plant

    Trucks moving from port to the factory — truck shortage

  • Road traffic3d · Received at Plant

    Weighed in, plant receipt raised — behind plan

Voyage

Loading map…

Stages

  1. Order ConfirmedPlanned 30 Mar 2026 · Actual 30 Mar 2026

    Owner: Procurement. Purchase order placed with the supplier

    • Purchase order placed30 Mar 2026
  2. Vessel AssignedPlanned 31 Mar 2026 · Actual 31 Mar 2026

    Owner: Supplier. Supplier has named the ship and we have accepted it

    • Vessel named31 Mar 2026
  3. Loaded at OriginPlanned 10 Apr 2026 · Actual 11 Apr 2026 · 1 day late
    Supplier delay at origin · 1d

    Owner: Supplier. Cargo aboard, Bill of Lading issued — behind plan

    • Bill of LadingVerified
    • Commercial invoiceVerified
    • Certificate of originVerified
    • Loading finished11 Apr 2026
    • Bill of Lading issued11 Apr 2026
  4. At SeaPlanned 14 Apr 2026 · Actual 16 Apr 2026 · 2 days late
    Weather on the voyage · 2d

    Owner: Shipping line. Sailing from China or Australia to India — weather

    • Sailed16 Apr 2026
  5. At Indian PortPlanned 28 Apr 2026 · Actual 30 Apr 2026 · 2 days late
    Barge transfer wait · 2d

    Owner: Port operations. Arrived, unloading — includes barge transfer where the port is shallow — behind plan

    • Arrived at Indian port30 Apr 2026
  6. Customs ClearedPlanned 07 May 2026 · Actual 11 May 2026 · 4 days late
    Customs assessment queue · 4d

    Owner: Customs agent. Bill of Entry assessed, duty paid, cargo released — clearance queue

    • Bill of EntryVerified
    • Customs cleared11 May 2026
  7. Road to PlantPlanned 10 May 2026 · Actual 14 May 2026 · 4 days late
    Truck shortage · 4d

    Owner: Transporter. Trucks moving from port to the factory — truck shortage

    • E-way billVerified
    • First truck dispatched14 May 2026
  8. Received at PlantPlanned 22 May 2026 · Actual 25 May 2026 · 3 days late
    Road traffic · 3d

    Owner: Plant stores. Weighed in, plant receipt raised — behind plan

    • Plant receiptVerified
    • Plant receipt raised25 May 2026