ANCHORLINE
Demo date · 20 Aug 2026
What am I looking at?

What one tonne of this material actually cost by the time it was standing in the plant yard. The waterfall builds it up from the price we paid the seller, through freight, port handling, duty, demurrage and road transport. It is compared against what was budgeted, and the difference is explained line by line. Quantity shortfall comes first in that explanation because it changes the denominator every other line is divided by.

Per tonne, estimated and actual
Total cost divided by the quantity that actually arrived at the plant, not by what was shipped.
Variance
Actual against budget, in rupees per tonne and as a percentage. Positive means it cost more than planned.
Recoverable
IGST. Paid in cash but reclaimed, so it is shown separately and kept out of the cost per tonne.
Memo
The value of material lost in transit. It is not an extra invoice; it is already reflected in the fact that fewer tonnes carry the same spend.

Read the full guide for this screen · written for Commercial and finance

PCL-2026-0530

Low Ash Metallurgical Coke · 37,500.000 MT · CFR Haldia · MV Eastern Dawn (IMO 9785237) · B/L BL/0530 dated 24 Dec 2025

Estimated per tonne

₹29,721.00

Actual per tonne

₹30,759.00

Variance per tonne

+₹1,038.00

3.49 % against estimate

Parcel total

₹1,14,30,97,009.82

+₹3,86,00,567.00 against estimate

Per-tonne figures divide by 37,162.500 MT Goods receipt note at the plant.

How the tonne is built

Each bar adds to the one before it. The final bar is the landed cost of one tonne of material standing in the plant yard.

Loading chart…

What moved the number

Ranked by rupees per tonne. Quantity shortfall comes first because it changes the denominator every other line is divided by.

  1. 1. Quantity shortfall+₹276.00 / MT

    337.5 MT of the Bill of Lading quantity never reached the plant. The same spend is now divided over fewer tonnes, so every remaining tonne carries more.

  2. 2. Goods value+₹620.00 / MT

    Budgeted ₹24,780/MT, came in at ₹25,400/MT.

  3. 3. Ocean & lighterage+₹193.00 / MT

    Budgeted ₹1,855/MT, came in at ₹2,048/MT.

  4. 4. Port & handling+₹109.00 / MT

    Budgeted ₹1,016/MT, came in at ₹1,125/MT.

  5. 5. Demurrage+₹50.00 / MT

    Nothing was budgeted for this. It is entirely an overrun.

  6. 6. Duties+₹35.00 / MT

    Budgeted ₹1,369/MT, came in at ₹1,404/MT.

Cost lines

Grouped into the buckets used by the waterfall. Open a bucket to see the individual estimated and actual lines behind it.

Goods value82.6 % of totalest ₹24,780.00/MTact ₹25,400.00/MT+₹620.00/MT
LineNatureCounterpartyIncurredPer tonneAmount
Goods valueACT/0530/02ActualJiangsu Hengrui Resources Co. Ltd12 Feb 2026 00:00 +05:30₹25,400.00₹94,39,27,500.00
Goods valueEstimatedJiangsu Hengrui Resources Co. Ltd24 Dec 2025 00:00 +05:30₹24,780.00₹92,08,86,750.00
Ocean & lighterage6.7 % of totalest ₹1,855.00/MTact ₹2,048.00/MT+₹193.00/MT
LineNatureCounterpartyIncurredPer tonneAmount
Marine insuranceACT/0530/04ActualThe New India Assurance Co. Ltd12 Feb 2026 00:00 +05:30₹119.00₹44,22,337.50
LighterageACT/0530/06ActualHooghly Floating Cranes Pvt Ltd12 Feb 2026 00:00 +05:30₹1,080.00₹4,01,35,500.00
Floating craneACT/0530/08ActualHooghly Floating Cranes Pvt Ltd12 Feb 2026 00:00 +05:30₹465.00₹1,72,80,562.50
Barge freightACT/0530/10ActualHooghly Floating Cranes Pvt Ltd12 Feb 2026 00:00 +05:30₹384.00₹1,42,70,400.00
Marine insuranceEstimatedThe New India Assurance Co. Ltd24 Dec 2025 00:00 +05:30₹115.00₹42,73,687.50
LighterageEstimatedHooghly Floating Cranes Pvt Ltd24 Dec 2025 00:00 +05:30₹960.00₹3,56,76,000.00
Floating craneEstimatedHooghly Floating Cranes Pvt Ltd24 Dec 2025 00:00 +05:30₹410.00₹1,52,36,625.00
Barge freightEstimatedHooghly Floating Cranes Pvt Ltd24 Dec 2025 00:00 +05:30₹370.00₹1,37,50,125.00
Port & handling3.7 % of totalest ₹1,016.00/MTact ₹1,125.00/MT+₹109.00/MT
LineNatureCounterpartyIncurredPer tonneAmount
Port duesACT/0530/12ActualEastport Shipping Agency12 Feb 2026 00:00 +05:30₹212.00₹78,78,450.00
WharfageACT/0530/14ActualEastport Shipping Agency12 Feb 2026 00:00 +05:30₹158.00₹58,71,675.00
StevedoringACT/0530/16ActualBengal Stevedores Company12 Feb 2026 00:00 +05:30₹506.00₹1,88,04,225.00
Plot rentACT/0530/18ActualEastport Shipping Agency12 Feb 2026 00:00 +05:30₹139.00₹51,65,587.50
Customs house agent feeACT/0530/20ActualBengal Clearing & Forwarding Pvt Ltd12 Feb 2026 00:00 +05:30₹34.00₹12,63,525.00
Survey feeACT/0530/22ActualSGS India Pvt Ltd12 Feb 2026 00:00 +05:30₹47.00₹17,46,637.50
DocumentationACT/0530/24ActualBengal Clearing & Forwarding Pvt Ltd12 Feb 2026 00:00 +05:30₹29.00₹10,77,712.50
Port duesEstimatedEastport Shipping Agency24 Dec 2025 00:00 +05:30₹205.00₹76,18,312.50
WharfageEstimatedEastport Shipping Agency24 Dec 2025 00:00 +05:30₹158.00₹58,71,675.00
StevedoringEstimatedBengal Stevedores Company24 Dec 2025 00:00 +05:30₹470.00₹1,74,66,375.00
Plot rentEstimatedEastport Shipping Agency24 Dec 2025 00:00 +05:30₹88.00₹32,70,300.00
Customs house agent feeEstimatedBengal Clearing & Forwarding Pvt Ltd24 Dec 2025 00:00 +05:30₹34.00₹12,63,525.00
Survey feeEstimatedSGS India Pvt Ltd24 Dec 2025 00:00 +05:30₹41.00₹15,23,662.50
DocumentationEstimatedBengal Clearing & Forwarding Pvt Ltd24 Dec 2025 00:00 +05:30₹20.00₹7,43,250.00
Duties4.6 % of totalest ₹1,369.00/MTact ₹1,404.00/MT+₹34.00/MT
LineNatureCounterpartyIncurredPer tonneAmount
Basic Customs DutyACT/0530/32ActualBengal Clearing & Forwarding Pvt Ltd12 Feb 2026 00:00 +05:30₹1,276.00₹4,74,17,491.88
Social Welfare SurchargeACT/0530/34ActualBengal Clearing & Forwarding Pvt Ltd12 Feb 2026 00:00 +05:30₹128.00₹47,41,749.19
Basic Customs DutyEstimatedBengal Clearing & Forwarding Pvt Ltd24 Dec 2025 00:00 +05:30₹1,245.00₹4,62,58,021.88
Social Welfare SurchargeEstimatedBengal Clearing & Forwarding Pvt Ltd24 Dec 2025 00:00 +05:30₹124.00₹46,25,802.19
Demurrage0.2 % of totalest ₹0.00/MTact ₹50.00/MT+₹50.00/MT
LineNatureCounterpartyIncurredPer tonneAmount
DemurrageDisputedACT/0530/36AccruedJiangsu Hengrui Resources Co. Ltd23 Feb 2026 00:00 +05:30₹50.00₹18,72,125.00
Inland2.3 % of totalest ₹689.00/MTact ₹720.00/MT+₹31.00/MT
LineNatureCounterpartyIncurredPer tonneAmount
Road freightACT/0530/26ActualEastern Haulage Logistics12 Feb 2026 00:00 +05:30₹638.00₹2,37,09,675.00
Plant handlingACT/0530/28ActualInternal12 Feb 2026 00:00 +05:30₹82.00₹30,28,743.75
Road freightEstimatedEastern Haulage Logistics24 Dec 2025 00:00 +05:30₹610.00₹2,26,69,125.00
Plant handlingEstimatedInternal24 Dec 2025 00:00 +05:30₹79.00₹29,35,837.50
Finance & other0.0 % of totalest ₹12.00/MTact ₹13.00/MT+₹2.00/MT
LineNatureCounterpartyIncurredPer tonneAmount
Bank chargesACT/0530/30ActualState Bank of India12 Feb 2026 00:00 +05:30₹13.00₹4,83,112.50
Bank chargesEstimatedState Bank of India24 Dec 2025 00:00 +05:30₹12.00₹4,27,368.75

Outside the cost per tonne

Recoverable — input tax credit, not cost

₹18,00,91,634.14

Integrated GST paid at the border is claimed back as input tax credit against output GST. It leaves the bank account but never lands on the cost of the material, so it is excluded from every per-tonne figure above.

  • Integrated GST · ₹18,00,91,634.14 · ₹4,846.00/MT

Memo — value of material lost, already reflected in the per-tonne denominator

₹85,72,500.00

The rupee value of the material that never arrived. Adding it to the cost total would count the loss twice, because the tonnes it represents have already been removed from the denominator.

  • Transit loss · ₹85,72,500.00