What one tonne of this material actually cost by the time it was standing in the plant yard. The waterfall builds it up from the price we paid the seller, through freight, port handling, duty, demurrage and road transport. It is compared against what was budgeted, and the difference is explained line by line. Quantity shortfall comes first in that explanation because it changes the denominator every other line is divided by.

Per tonne, estimated and actual
Total cost divided by the quantity that actually arrived at the plant, not by what was shipped.
Variance
Actual against budget, in rupees per tonne and as a percentage. Positive means it cost more than planned.
Recoverable
IGST. Paid in cash but reclaimed, so it is shown separately and kept out of the cost per tonne.
Memo
The value of material lost in transit. It is not an extra invoice; it is already reflected in the fact that fewer tonnes carry the same spend.

Read the full guide for this screen · written for Commercial and finance

PCL-2026-0417

Low Ash Metallurgical Coke · 45,000.000 MT · CFR Haldia · MV Iron Meridian (IMO 9648233) · B/L HDC/JTG/2026/0417 dated 28 May 2026

Estimated per tonne

₹30,845.00

Actual per tonne

₹32,123.00

Variance per tonne

+₹1,278.00

4.14 % against estimate

Parcel total

₹1,43,30,31,842.00

+₹5,70,24,054.00 against estimate

Per-tonne figures divide by 44,610.400 MT Goods receipt note at the plant.

How the tonne is built

Each bar adds to the one before it. The final bar is the landed cost of one tonne of material standing in the plant yard.

Loading chart…

What moved the number

Ranked by rupees per tonne. Quantity shortfall comes first because it changes the denominator every other line is divided by.

  1. 1. Quantity shortfall+₹278.00 / MT

    389.6 MT of the Bill of Lading quantity never reached the plant. The same spend is now divided over fewer tonnes, so every remaining tonne carries more.

  2. 2. Goods value+₹1,025.00 / MT

    Budgeted ₹27,331/MT, came in at ₹28,356/MT.

  3. 3. Demurrage+₹68.00 / MT

    Nothing was budgeted for this. It is entirely an overrun.

  4. 4. Duties+₹63.00 / MT

    Budgeted ₹1,498/MT, came in at ₹1,561/MT.

  5. 5. Inland+₹50.00 / MT

    Budgeted ₹1,181/MT, came in at ₹1,231/MT.

  6. 6. Ocean & lighterage+₹44.00 / MT

    Budgeted ₹459/MT, came in at ₹503/MT.

Cost lines

Grouped into the buckets used by the waterfall. Open a bucket to see the individual estimated and actual lines behind it.

Goods value88.3 % of totalest ₹27,331.00/MTact ₹28,356.00/MT+₹1,025.00/MT
LineNatureCounterpartyIncurredPer tonneAmount
Goods valueACT/0417/01ActualJiangsu Hengrui Resources Co. Ltd17 Jul 2026 00:00 +05:30₹28,356.00₹1,26,49,91,212.00
Goods valueEstimatedJiangsu Hengrui Resources Co. Ltd28 Mar 2026 00:00 +05:30₹27,331.00₹1,21,92,63,392.80
Ocean & lighterage1.6 % of totalest ₹459.00/MTact ₹503.00/MT+₹44.00/MT
LineNatureCounterpartyIncurredPer tonneAmount
Marine insuranceACT/0417/02ActualThe New India Assurance Co. Ltd17 Jul 2026 00:00 +05:30₹24.00₹10,75,242.00
LighterageACT/0417/03ActualHooghly Floating Cranes Pvt Ltd17 Jul 2026 00:00 +05:30₹315.00₹1,40,46,208.00
Floating craneACT/0417/04ActualHooghly Floating Cranes Pvt Ltd17 Jul 2026 00:00 +05:30₹60.00₹26,95,000.00
Barge freightACT/0417/05ActualHooghly Floating Cranes Pvt Ltd17 Jul 2026 00:00 +05:30₹103.00₹46,08,912.00
Marine insuranceEstimatedThe New India Assurance Co. Ltd28 Mar 2026 00:00 +05:30₹23.00₹10,32,232.32
LighterageEstimatedHooghly Floating Cranes Pvt Ltd28 Mar 2026 00:00 +05:30₹302.00₹1,34,84,359.68
Floating craneEstimatedHooghly Floating Cranes Pvt Ltd28 Mar 2026 00:00 +05:30₹35.00₹15,40,000.00
Barge freightEstimatedHooghly Floating Cranes Pvt Ltd28 Mar 2026 00:00 +05:30₹99.00₹44,24,555.52
Port & handling1.2 % of totalest ₹360.00/MTact ₹389.00/MT+₹29.00/MT
LineNatureCounterpartyIncurredPer tonneAmount
Port duesACT/0417/06ActualInternal17 Jul 2026 00:00 +05:30₹187.00₹83,45,485.00
StevedoringACT/0417/07ActualBengal Stevedores Company17 Jul 2026 00:00 +05:30₹143.00₹63,71,284.00
Plot rentACT/0417/08ActualInternal17 Jul 2026 00:00 +05:30₹34.00₹14,96,000.00
Customs house agent feeACT/0417/09ActualBengal Clearing & Forwarding Pvt Ltd17 Jul 2026 00:00 +05:30₹9.00₹3,85,000.00
Survey feeACT/0417/10ActualSGS India Pvt Ltd17 Jul 2026 00:00 +05:30₹14.00₹6,42,000.00
DocumentationACT/0417/11ActualInternal17 Jul 2026 00:00 +05:30₹3.00₹1,28,000.00
Port duesEstimatedInternal28 Mar 2026 00:00 +05:30₹180.00₹80,11,665.60
StevedoringEstimatedBengal Stevedores Company28 Mar 2026 00:00 +05:30₹137.00₹61,16,432.64
Plot rentEstimatedInternal28 Mar 2026 00:00 +05:30₹18.00₹8,16,000.00
Customs house agent feeEstimatedBengal Clearing & Forwarding Pvt Ltd28 Mar 2026 00:00 +05:30₹8.00₹3,69,600.00
Survey feeEstimatedSGS India Pvt Ltd28 Mar 2026 00:00 +05:30₹14.00₹6,16,320.00
DocumentationEstimatedInternal28 Mar 2026 00:00 +05:30₹3.00₹1,22,880.00
Duties4.9 % of totalest ₹1,498.00/MTact ₹1,561.00/MT+₹62.00/MT
LineNatureCounterpartyIncurredPer tonneAmount
Basic Customs DutyACT/0417/12ActualInternal17 Jul 2026 00:00 +05:30₹1,419.00₹6,33,03,323.00
Social Welfare SurchargeACT/0417/13ActualInternal17 Jul 2026 00:00 +05:30₹142.00₹63,30,332.00
Basic Customs DutyEstimatedInternal28 Mar 2026 00:00 +05:30₹1,362.00₹6,07,71,190.08
Social Welfare SurchargeEstimatedInternal28 Mar 2026 00:00 +05:30₹136.00₹60,77,118.72
Demurrage0.2 % of totalest ₹0.00/MTact ₹68.00/MT+₹68.00/MT
LineNatureCounterpartyIncurredPer tonneAmount
DemurrageDisputedACT/0417/15ActualJiangsu Hengrui Resources Co. Ltd17 Jul 2026 00:00 +05:30₹68.00₹30,28,385.00
DemurrageDisputedEstimatedJiangsu Hengrui Resources Co. Ltd28 Mar 2026 00:00 +05:30₹0.00₹0.00
Inland3.8 % of totalest ₹1,181.00/MTact ₹1,231.00/MT+₹49.00/MT
LineNatureCounterpartyIncurredPer tonneAmount
Road freightACT/0417/16ActualEastern Haulage Logistics17 Jul 2026 00:00 +05:30₹1,183.00₹5,27,60,160.00
Plant handlingACT/0417/17ActualInternal17 Jul 2026 00:00 +05:30₹48.00₹21,41,299.00
Road freightEstimatedEastern Haulage Logistics28 Mar 2026 00:00 +05:30₹1,135.00₹5,06,49,753.60
Plant handlingEstimatedInternal28 Mar 2026 00:00 +05:30₹46.00₹20,55,647.04
Finance & other0.1 % of totalest ₹15.00/MTact ₹15.00/MT+₹1.00/MT
LineNatureCounterpartyIncurredPer tonneAmount
Bank chargesACT/0417/18ActualState Bank of India17 Jul 2026 00:00 +05:30₹15.00₹6,84,000.00
Bank chargesEstimatedState Bank of India28 Mar 2026 00:00 +05:30₹15.00₹6,56,640.00

Outside the cost per tonne

Recoverable — input tax credit, not cost

₹24,04,26,020.00

Integrated GST paid at the border is claimed back as input tax credit against output GST. It leaves the bank account but never lands on the cost of the material, so it is excluded from every per-tonne figure above.

  • Integrated GST · ₹24,04,26,020.00 · ₹5,389.00/MT

Memo — value of material lost, already reflected in the per-tonne denominator

₹1,09,52,046.00

The rupee value of the material that never arrived. Adding it to the cost total would count the loss twice, because the tonnes it represents have already been removed from the denominator.

  • Transit loss · ₹1,09,52,046.00