The contract gives us a fixed number of hours to unload the ship, free of charge. Run past it and the shipowner charges demurrage for every day over. This screen recalculates that time from the Statement of Facts, event by event, and puts our number next to the seller's claim. Where the two differ, the reason is a specific event whose treatment we dispute — usually rain or waiting for barges.

Allowed
Cargo quantity divided by the contractual discharge rate. If the contract says 8,000 tonnes a day and the cargo is 45,000 tonnes, we get 135 hours.
Used
Time actually consumed, after excepted periods are stripped out. Sundays, holidays and weather come out if the contract says they do.
Claimed against computed
What the seller says we owe, against what the same events give when the contract is applied strictly. The gap is what a rebuttal is worth.
Rebuttal window
The days left to dispute the claim. Miss it and the claim is deemed accepted in full, whatever the facts say.

Read the full guide for this screen · written for The laytime analyst

PCL-2026-0417

Low Ash Metallurgical Coke · 45,000.000 MT · CFR Haldia · MV Iron Meridian (IMO 9648233) · B/L HDC/JTG/2026/0417 dated 28 May 2026

Seller claims
$77,750.00
103.667 h on dem.
Our position
$34,250.00
45.667 h on dem.
In dispute
$43,500.00
58.000 h

Laytime ribbon

One cell per hour from commencement to completion. Hover for the governing event; click to open the evidence document panel.

18 Jun19 Jun20 Jun21 Jun22 Jun23 Jun24 Jun25 Jun26 Jun27 Jun28 Jun29 Jun30 JunDEMURRAGE BEGINS · 27 Jun 2026 14:00
  • Counts
  • Excepted
  • Disputed exception
  • On demurrage

Exception ledger

Disputed total 58.000 h

FromToHoursReasonContract basisEvidenceBuyerSellerDisputed
21 Jun 2026 00:00 +05:3022 Jun 2026 00:00 +05:3024.000 hSunday — SHEXrateBasis SHEXMANUAL ENTRYExceptedAgreedNo
22 Jun 2026 02:15 +05:3023 Jun 2026 09:45 +05:3031.500 hWeather stoppageweatherStoppagesCount = falseDOC-0417-METEOExceptedSeller contends monsoon interruption is a normal incident of discharge at Haldia and counts as laytime.Yes
25 Jun 2026 14:00 +05:3026 Jun 2026 06:30 +05:3016.500 hFloating crane breakdownnot the buyer's riskDOC-0417-CRANEExceptedSeller contends floating crane performance is the buyer's arrangement under the lighterage clause.Yes
26 Jun 2026 18:00 +05:3027 Jun 2026 04:00 +05:3010.000 hFirst shifting anchorage → berthfirstShiftingCounts = falseDOC-0417-SOFExceptedSeller counts shifting from anchorage to berth as used laytime.Yes
28 Jun 2026 00:00 +05:3029 Jun 2026 00:00 +05:3024.000 hSunday — SHEXrateBasis SHEXMANUAL ENTRYExceptedAgreedNo

Rebuttal

Deadline 03 Sep 2026 00:00 +05:30
13d remainingStatus UNDER REVIEW