Bulk cargo is weighed several times between the load port and the plant, and it never weighs the same twice. This screen follows the chain — Bill of Lading, draft survey at discharge, weighbridge at the plant — and shows where the material went missing. Each leg is measured in basis points against the tolerance the contract allows for that leg.

Chain
Each measurement in the order it was taken, with the change from the previous one. A leg outside its tolerance is flagged.
Attribution
How much of the shortfall belongs to moisture, to handling losses at the anchorage, and to road transit.
Dry basis
Weight after deducting moisture. If the contract prices on a dry basis, this is the number we pay against, not the wet weight.

Read the full guide for this screen · written for Operations and commercial

PCL-2026-0417

Low Ash Metallurgical Coke · 45,000.000 MT · CFR Haldia · MV Iron Meridian (IMO 9648233) · B/L HDC/JTG/2026/0417 dated 28 May 2026

B/L45,000.000 MTReceived44,610.400 MT
Loss389.600 MT· 0.866 %· ₹1.10 Cr at goods value

No individual leg breached tolerance. Cumulative loss was 0.866%.

Measurement chain

  1. Contract45,000.000 MT28 Mar 2026 00:00 +05:30CTR-SM-2026-039
    0.000 MT+0.000 %Contract → B/LUnattributed
  2. Bill of Lading45,000.000 MT28 May 2026 00:00 +05:30HDC/JTG/2026/0417
    +38.500 MT+0.086 %B/L → load surveySellertol 0.500 %
  3. Load draft survey45,038.500 MT28 May 2026 00:00 +05:30CCICCCIC/JTG/26/8841
    170.300 MT0.378 %Ocean & transloadingCarriertol 0.500 %
  4. Discharge draft survey44,868.200 MT20 Jun 2026 00:00 +05:30SGS India Pvt LtdSGS/HDC/26/1102
    65.600 MT0.146 %Shore handlingStevedoretol 0.200 %
  5. Shore weighment44,802.600 MT30 Jun 2026 00:00 +05:30HDC/WB/26/4471
    90.600 MT0.202 %Plot storagePorttol 0.250 %
  6. Plot dispatch44,712.000 MT14 Jul 2026 00:00 +05:30HDC/PD/26/0993
    101.600 MT0.227 %Road transitTransportertol 0.300 %
  7. Weighbridge net44,610.400 MT16 Jul 2026 00:00 +05:30JAM/WB/26/11284
    0.000 MT+0.000 %GRN postingUnattributed
  8. GRN44,610.400 MT17 Jul 2026 00:00 +05:305000418822

Loss attribution

  • Ocean & transloading
    170.300 MT
    Carrier
  • Shore handling
    65.600 MT
    Stevedore
  • Plot storage
    90.600 MT
    Port
  • Road transit
    101.600 MT
    Transporter

The four inland and ocean legs lose 428.100 MT. Load-survey gain of 38.500 MT offsets that to a net B/L → GRN loss of 389.600 MT.

Dry basis

Wet outturn
44,868.200 MT
Discharge moisture
5.40 %
Dry outturn
42,445.317 MT

Pricing is on the dry figure. Quality and price adjustment